Maintenance tasks
Street:
• Potholed roads
• Mowed ditches
• Worked with contractor to replace two culverts
• Worked with contractor to repair failing catch basin structure
• Installed culvert on Layton Av.
• Removed several trees from roads after storm
• Repaired washouts on Pilar Rd
• Picked up several appliances along roadside
Sewer:
• Read pump run times at all of the lift stations
Park and Recreation:
• Inspected playground equipment
• Mowed and weed whipped all City property
• Removed stakes from rotted steps at Wind in the Pines
• Raised dock at Goose Lake
• Removed tree from the Goose Lake Landing
• Installed grommets and put up Farmer's Market banners
Water:
• Read water meters for Uptown system
Equipment and Building:
• Performed monthly OSHA inspections
• Fixed radiator leak on the John Deere 6410 Tractor(302-99)
Miscellaneous:
� Located City utilities
• Attended safety meeting
Management tasks
Street:
• Met with resident and Watershed District about a culvert issue
• Met with residents, contractor,and Watershed District about erosion issues on Layton Av.
• Worked on proposal about an erosion issue for the Watershed District
• Corresponded with Cedar Cliff residents about dust control
• Scheduled street sweeping with contractor
• Scheduled and supervised the bituminous patching
• Ordered street signs
• Corresponded with City Engineer about several projects
• Scheduled contractor to have a ditch reshaped on Larkspur Av.
• Scheduled the Gravel Resurfacing Project
• Updated the City's culvert and driveway requirements
Sewer:
• Worked with EcoCheck on the Uptown and Bliss systems
• Scheduled the septic and pump tank inspections for the 201 system with EcoCheck
• Sent out inspection notice letters
• Scheduled the replacement of the Bliss Drainfield transformer with Xcel
• Worked on the 201 and Uptown budgets
• Corresponded with engineer about the final improvements to the Uptown System
Park and Recreation:
• Reviewed Park and Recreation budget for 2014
• Met with several people about a proposed trail at Hay Lake
Equipment and Building:
• Researched jack hammers prices
• Scheduled the bi-annual inspection of the ANSUL system in the Community Center kitchen
• Met with electricians to supply power to the ANSUL system in the Community Center kitchen
• Met with several roofing contractors about the Community Center roof
• Scheduled the lift to be installed
Miscellaneous:
• Called in locates for several projects
• Gathered information on surplus items to be sold
• Met with Watershed to discuss several projects
• Scheduled the final warning siren to be activated