Loading...
10.d1 Engineering Updates 8-15-2023 City of Scandia Engineering Updates 8/15/2023 Engineering italics = old information · Capital Improvement Plan – Road Tour  Completed a road tourn on April 3, 2023 with Public Works to review the conditions of the road due to the excessive deterioration with the numerous freeze thaw cycles and rain events this winter went through. Cost estimates have been prepared and working with Public Works on review of the Capital Improvement Plan. · 2023 Crack Filling and Seal Coat Project  Allied Blacktop Company, Person Bros., Inc., and Fahrner Asphalt Sealers, LLC submitted bids on this project. The project has been awarded to Allied Blacktop Company for $139,576.50.  Final sweeping has been completed. Railroad cross striping is scheduled to be completed on Tuesday August 8th. · 2023 Street Improvement Project  Contracts have been signed by all parties and distributed to the City already. Astech will receive their copies at the precon meeting held on Thursday, April 13th. Astech will have their project construction schedule and list of subcontractors prepared for this meeting.  Silt fence and biologs were installed the morning of Tuesday, May 2nd. Reclaiming started on Tuesday, May 2nd and was completed by Thursday, May 4th. Driveways were removed and ramped for resident access on Monday, May 8th. Pipe work is anticipated to begin Thursday, May 11th.  Subgrade corrections took place the week of May 21st – 26th.  Base Course was paved May 31st – June 2nd.  Wear Course was paved June 8th – June 12th.  Project Punchlist will be created and sent to Astech before the end of this week.  Pay application #1 had a cutoff date of May 26th and will be included as an agenda item at the June council meeting.  Pavement Re-evaluation has been tentatively scheduled for mid/late August. No firm date has been confirmed with the Contractor yet.  Construction to correct pavement is still scheduled for early September.  Restoration punchlist will be checked once pavement evaluation has taken place. · 2022 Street Improvement Project (Melanie Trail N and 238th Street N)  Punchlist work has been completed, and final documents have been produced.  Final project closeout document package will be a part of the August 15th Council Meeting Agenda. · Tii Gavo Development Phase II  Watershed permit has been obtained and grading work began on Tuesday July 11th. BMI will have staff on site for public infrastructure inspections.  Storm Sewer Improvement have been completed.  Sanitary Force main spot work is still in progress.  Sand and Gravel has been placed and compacted but still will need tolerance work completed. · Bliss Drainfield System  The final permit has been issued. The assumption is that we’ll end up on Track 2, with required system improvements due to the nitrate issue. Only thing that needs to take place in the next 6 months (February 28, 2022) is for new flow meters to be installed at the system, something we’ll begin working on. At the one year mark (September 1, 2022), we’ll need to have a Facility Evaluation Report drafted to summarize the system’s ability or inability to meet the nitrate limit.  New flow meters were installed by Public Works at the beginning of 2022 and specific flows to the three drainfield cells is now being monitored. Some additional nitrate testing was also performed in August 2022 to provide additional data points and to get an idea of how much nutrient removal is currently taking place through the sand filters.  As of September 1, 2022, the Facility Evaluation Report has been sent to the MPCA. We await their review, but based on the monitoring well samples taken throughout the last year it appears we’ll be on Track 2, with improvements to the system needed to deal with the nitrate issue. Assuming this is the case, the next step will be to complete a full Facility Plan by August of 2023 which evaluates the facility and its performance as a whole and provides options/recommendations for improvements to be made. This is required by Track 2 but is also the next step in obtaining PFA funding for the project.  We met with MPCA on December 16, 2022 to discuss funding options and laid out a schedule to complete a facility plan and apply for Point Source Implementation Grant (PSIG) funding.  City Council authorized work to complete the facility plan on January 4, 2023. Facility plan to be submitted by March 3, 2023. Also, Council authorized BMI to complete permit documents for permit modification due to added treatment for nitrate removal.  Testified at the Capitol on Wednesday, March 1, 2023 requesting funding for the Bliss Wastewater Treatment Facility.  Facility plan has been submitted for the City of Scandia’s Bliss Wastewater Treatment Facility along with and IUP request and PPL application to the Minnesota Public Facilities Authority on Friday, March 3, 2023. As of June 22, the MPCA has issued preliminary approval of this facility plan.  Authorization to prepare plans & specifications for the Bliss Wastewater Treatment Facility Nitrogen Removal improvements was requested and approved at the May 16 City Council meeting.  Project plans and specifications are currently being prepared.  2024 Capital Bonding Request application has been prepared.  PSIG Funding application was submitted at the end of July (2023). · Washington County – Manning Ave/CSAH 15 – Sinusoidal Rumble Strips & Striping Project  Washington County has completed their 90% construction plans for the centerline sinusoidal rumble strip (mumble strips) project planned for construction in 2023. Washington County received Highway Safety Improvement Program grant funds for this project. This project includes installing center line sinusoidal rumble strips along County Highway 15 (Manning Ave) from County Highway 12 (75th St) to 240th Street (County line) and new centerline striping.  Washington County has awarded the project and construction is planned for after the Labor Day weekend. · Floodplain Risk Assessment  Watershed District has received notification from the MPCA they did not receive the grant that was applied for.  CMSCWD Board is considering allocating funding for the Risk Assessment in 2024 at their 2024 CMSCWD Budget Workshop.  The draft 2024 CMSCWD budget currently includes funding to address model data gaps for the Big Marine Lake outlet, Carnelian Channel, and Carnelian Creek flowages. This is the first step in a multi-year process to complete the Floodplain Risk Assessment. · Bliss Addition Stormwater Planning  Watershed still working toward 90% plans based on City Staff input received in November 2022.  City and Watershed have completed the MOU.  Watershed/Consultants redesigning project practices after a final utility meet locate identified previously un-marked conflicts.  Due to delays caused by utilities not marked on the initial locate, the CMSCWD will delay construction to 2024. Upon completion of the final plans, submittals will be prepared to the City for their review. CMSCWD anticipates soliciting bids in October 2023.  Project still waiting on the utility company for relocates for Bliss Addition. · CLFLWD & Scandia Staff Quarterly Meetings  Meeting on May 11, 2021 covered the following topics: · Permitting Update (Nick) · Roadway Projects (Ken) · Bone Lake projects status: SE wetland restorations, NE wetland restoration, agricultural practices (Blayne) · FY22 Clean Water Fund grant award – Moody Lake projects (Emily/Blayne) · Greenway Corridor Planning & Parks Update (Nick) · CMSCWD Management Plan (Mike Isensee) · Regional Update – Highway 243 Osceola Bridge  Project website: http://www.dot.state.mn.us/metro/projects/hwy243osceola/index.html  Public Meeting scheduled for May 10, 2023, 5:00pm-7:00pm at the Osceola Village Board Room  Schedule: · Environmental documentation and preliminary design: 2021 through 2023 · Final design: 2023 through 2025 · Anticipated construction: 2026 through 2027 Denise Workcuff Dmitry Tomasevich Communications and Engagement Project manager denise.workcuff@state.mn.us dmitry.tomasevich@state.mn.us 651-775-0025 651-245-4406