5.a 3 Ordinance No 171 Solar Amended Draft 7.5.16
Ordinance No. 162 Page 1 of 6
CITY OF SCANDIA
ORDINANCE NO.: 171
AN ORDINANCE AMENDING
ORDINANCE NO. 122, THE SCANDIA DEVELOPMENT CODE,
CHAPTER 2, SECTION 4.34, REGARDING SOLAR FARMS AND
COMMUNITY SOLAR GARDENS
The City Council of the City of Scandia, Washington County, Minnesota hereby ordains:
Section 1. Amendment. Ordinance No. 122, the City of Scandia Development Code
(“Development Code” or “Code”), Chapter Two, Section 4.34, Solar Farms and Community
Solar Gardens, shall be amended as follows:
4.33 Solar Farms and Community Solar Gardens. Solar farms and community solar
gardens shall comply with all of the following standards:
(1) Districts and Permits
(A) Solar farms and community solar gardens are allowed within the Agriculture
Core (AG C), Agriculture Preserves (AP), and General Rural (GR) zoning
districts and require a Conditional Use Permit. In the AP District, the use is
permitted on parcels where the Agriculture Preserves Program status and
agreements permit this use.
(B) The City prohibits solar farms and community solar gardens within the
following districts:
1. Within areas designated as Shoreland Districts by the Department of
Natural Resources and the City of Scandia Shoreland Ordinance.
2. Within six hundred (600) feet of areas designated or formally protected
from development by Federal, State or County agencies as wildlife habitat,
wildlife management areas, or designated as National Wild and Scenic
land or corridor.
3.2. Within wetlands to the extent required by the Minnesota Wetlands
Conservation Act.
4.3. Within the Floodplain District.
(2) Accessory solar farm and community solar garden uses are exempt from the
Residential and Agricultural Accessory Structure standards regarding the square
footage and number of structures permitted on a parcel, but must conform to the
setback and lot coverage standards in this Development Code.
Ordinance No. 162 Page 2 of 6
(3) Permit Application
(A) Existing Site Plans Required. The applicant for a solar farm or community
solar garden shall submit a detailed site plan of existing conditions, showing
site boundaries; existing access roads, driveways, and easements; existing
structures; setbacks; surface water drainage patterns, floodplains, Shoreland
districts, delineated wetlands, toe and top of bluffs, ordinary high water mark
and other protected natural resources; existing vegetation, soil types,
topography (2-foot contour intervals), and all other items required in Chapter
1, Section 5 of this Code for Conditional/Interim Use Permit applications or
by the City. The Existing Site Plan shall include a graphic scale not less than
1:100 and a north arrow.
(B) Proposed Site Plan Required. The applicant shall also submit a site plan of
proposed conditions, including the proposed number, location and spacing of
solar panels; proposed height of panels; location of access roads; planned
location of underground or overhead electric lines connecting the solar farm to
the building, substation or other electric load; new electrical equipment other
than at the existing building or substation that is the connection point for the
solar farm; proposed stormwater management facilities; proposed erosion and
sediment control measures, and other information as required by the City.
The Proposed Site Plan shall include a graphic scale not less than 1:100 and a
north arrow.
The application shall also include a vertical sketch elevation of the premises
accurately drawn to a scale identified on the drawing, depicting the proposed
solar energy conversion system and its relationship to the surrounding
topography and public roadways. The sketch shall depict the proposed
system’s relationship to structures on adjacent lots within 150 feet of the
parcel boundary (if any). The sketch elevation shall include a graphic scale
not less than 1:50, or as needed to clearly show the vertical relationship
between the proposed solar facilities and structures on adjacent lots.
(C) Use of Public Roads. The applicant shall obtain all necessary approvals from
the appropriate road authority for site access and driveways.
(D) Interconnection Agreement. The applicant shall complete an interconnection
agreement with a local utility and provide a copy of the agreement to the City
before approval of electrical, building, or other required permits. The system
operator shall provide a visible external disconnect if required by the utility.
(E) Liability Insurance. The applicant shall maintain a current general liability
policy covering bodily injury and property damage with limits of at least $1
million per occurrence and $1 million in the aggregate, and provide proof that
it meets the insurance requirement to the city.
Ordinance No. 162 Page 3 of 6
(F) Decommissioning Plan. The applicant shall submit a decommissioning plan
to ensure that facilities are properly removed after their useful life. If the solar
energy system remains nonfunctional or inoperative for a continuous period of
one year, the system shall be deemed to be abandoned and shall constitute a
public nuisance. The plan shall include provisions for removal of all
structures and foundations, restoration of soil and vegetation, and a plan
ensuring financial resources will be available to fully decommission the site.
The City may require the posting of a bond, letter of credit or the
establishment of an escrow account to ensure decommissioning.
(G) Payment In Lieu of Taxes. Notwithstanding that Minnesota Statutes Section
272.02, Subdivision 24 (or its successor) classifies real property upon which a
solar energy generating system is located that is used primarily for solar
energy production (subject to the production tax under Minnesota Statutes
Section 272.0295) as class 3a, the City may require the applicant to enter into
a Payment In Lieu of Taxes Agreement to compensate the City for any
prospective tax revenue that may be lost due to such reclassification.
(4) Performance Standards
(A) Solar farms which have a generating capacity of 50 megawatts of power or
more shall fall under the jurisdiction of the Minnesota Public Utilities
Commission. The limitations on the number or cumulative generating
capacity of community solar garden facilities is regulated by Minnesota
Statutes 216B.164 and related regulations.
(B) Solar farms and community solar gardens shall be located on a parcel of atthat
is at least 5 20 acres in size. The maximum size of the parcel(s) where a solar
farm or community solar garden is located shall be 80 acres.
(C) Solar farms and community solar gardens shall be in compliance with any all
applicable local, state and federal regulatory standards, including the State of
Minnesota Uniform Building Code, as amended; the National Electric Code,
as amended; the State Plumbing Code, as amended; the Minnesota Energy
Code, as amended.
(D) If the proposed solar farm or community solar garden is adjacent to areas
designed or formally protected from development by Federal, State, or County
agencies as a wildlife management area, scenic byway, or National Wild and
Scenic corridor, the applicant shall implement mitigation measures that would
protect the resource values of the designated wildlife area or scenic corridor as
a condition of approval. Such measures may include, but are not limited to,
maintaining wildlife travel corridors, setting the development back from the
right-of-way or stream corridor, using the natural topography to screen the
project, and retaining or planting vegetation that would obsure the view of the
energy project within the scenic corridor.
Ordinance No. 162 Page 4 of 6
(D)(E) All solar farms and community solar gardens shall comply with the
principal structure setback standards and lot coverage standard for the
applicable zoning district in which they are located. The City may require
wider setbacks, up to 100/150 feet from one or more parcel boundaries, if the
City determines that the wider setbacks are warranted by the potential impacts
to adjacent properties.
(E)(F) Solar farms and community solar gardens shall be setback a minimum of
200 feet from the centerline or 150 feet from the right-of-way of minor arterial
roadways, whichever is greater.
(F)(G) Ground-mounted solar energy systems shall not exceed fifteen feet (15’)
in height. Building-integrated solar energy systems shall not exceed the
maximum height permitted in the zoning district.
(H) Solar farms and gardens shall be located to the extent practicable on sites
where the proposed maximum elevation on the parcel(s) is no higher than the
highest elevation of adjacent roadways. If the elevations on the proposed site
are higher than adjacent roadway elevations, the applicant shall demonstrate
that the project shall be screened from view from adjacent roadways and
parcels using berming, existing vegetation, landscaping, or a combination
thereof.
(G)(I) Solar farms and community solar gardens shall be screened from view
from the public right of way to the extent possible practicable by setbacks,
berming, existing vegetation, landscaping, or a combination thereof. The City
may require that the solar arrays be screened from view from nearby or
affected properties using the same screening elements, and may require a
vegetative buffer up to 25’ in width and/or screening of up to ninety-five (95)
percent of the view of the solar arrays from adjacent parcels.
(H)(J) Solar farms and community solar gardens are subject to stormwater
management and erosion and sediment control best practices and NPDES
permit requirements, and shall obtain required permits from the MPCA, local
Watershed District, City and others.
(I)(K) The manufacturer’s engineer or another qualified engineer shall certify
that the foundation and design of the solar panels is within accepted
professional standards, given local soil and climate conditions.
(J)(L) Power and communication lines that are not defined in this ordinance as
Essential Services and running between banks of solar panels and to electric
substations or interconnections with buildings that are on adjacent parcels
shall be buried underground. Exemptions may be granted by the City in
instances where shallow bedrock, water courses or other elements of the
Ordinance No. 162 Page 5 of 6
natural landscape interfere with the ability to bury lines, or the distance to a
substation or other point of interconnection reasonable precludes burial.
(K)(M) All solar farm and community solar garden facilities shall be designed and
located in order to prevent reflective glare toward any inhabited buildings on
adjacent properties, as well as adjacent street rights-of-way. Steps to control
glare nuisance may include selective placement of the system, screening on
the side of the solar array facing the reflectors, reducing use of the reflector
system, or other remedies that limit glare. Solar farms utilizing a reflector
system shall conduct a glare study to identify the impacts of the system on
occupied buildings and transportation rights-of-way within a half mile of the
project boundary. The glare study shall also address aviation impacts.
(L)(N) The surface area of ground-mounted systems in combination with
driveways, structures and other impervious surfaces on the parcel shall not
exceed the maximum lot coverage standard of the applicable zoning district.
(M)(O) A clearly-visible warning sign concerning voltage must be placed at the
base of all pad-mounted transformers and substations. All mechanical
equipment, including any structure for batteries or storage cells, shall be
completely enclosed by a minimum eight (8) foot high fence with a self-
locking gate, and provided with screening in accordance with the landscaping
provisions of the Development Code.
(P) Solar farms and community solar gardens shall be enclosed by a fence,
barrier, or other appropriate means to prevent or restrict unauthorized persons
or vehicles from entering the parcel. Fences or barriers shall incorporate
wildlife-friendly design. The City will utilize recommendations from the
Minnesota DNR to determine if the fence design is wildlife-friendly.
(N)(Q) If the solar energy system remains nonfunctional or inoperative for a
continuous period of one year, the system shall be deemed to be abandoned
and shall constitute a public nuisance. The owner shall remove the abandoned
system at their expense after obtaining a demolition permit. Removal includes
the entire structure including transmission equipment.
Section 3. Effective Date. This ordinance shall be in full force and effect upon its adoption and
publication according to law.
Passed and adopted by the City Council of the City of Scandia this ________, 2015.
Randall Simonson, Mayor
Ordinance No. 162 Page 6 of 6
ATTEST:
Kristina Handt, Administrator/Clerk