8.d Engineering Updates 2016-8-16 City of Scandia Engineering Updates 8/16/2016 Engineering italics = old information • 2016 Street Improvements All work has been completed other than establishment of final restoration and minor punch list items. As a separate business item included on the agenda, Contractor’s Request for Payment No. 3 has been included. • 2016 Seal Coat and Crack Filling Project Crack filling work has been completed. Seal coating work is scheduled for Friday (August 12 th ) unless weather pushes it to the following Monday or Tuesday. All the Seal Coating work should be completed within a day and a half, initial sweeping will be completed 3 – 8 days later, and the second sweeping 30 days after the initial sweeping. • Bliss Drainfield System A memo was prepared in response to a June 9, 2016 letter from the MPCA regarding the Compliance Evaluation Inspection of the Scandia Bliss Wastewater Treatment Facility on May 24, 2016. The purpose of the memo was to address the concerns regarding the Nitrogen Mitigation Plan. Seth Peterson was onsite with City Staff on August 11 th to review the physical conditions of the Bliss Drainfield System and to identify items that need to be corrected that can be budgeted within the Capital Improvement Plan.