Loading...
04. Replacement of Cold Storage Building Staff Report Date of Meeting: November, 6th 2024 To: City Council From: Mike Hinz, Fire Chief and Charles Fischer Public Works Director Re: Replacement Cold Storage Building Background: The current cold storage building is a 50’ x 60’ steel structure and sits on the southeast corner of the city hall parking lot. The building is scheduled to be replaced in the CIP with a cost estimate of $160,000. Currently public works uses the building to store equipment and materials that are used seasonally or infrequently such as the grader, hot mix trailer and many other items. One of the major issues with the current building is the location. To use or retrieve anything in the building you must drive there and park or use the loader and/or trailer to bring items to the main Fire/Public Works building. Another issue is that it is not in a sufficient location to store many of the items that are currently stored outside at the Fire/Public Works building. The insufficiency of the building location increases the amount of time required to complete projects or utilize for storage of major components or attachments to have readily at hand. Existing attachments or components of equipment are currently stored outside behind the Fire/Public Works building which decreases the useful life of the equipment and/or increases maintenance requirements. The fire department would also like to use the new building to store training equipment and apparatuses with other items that are not used as often. The Fire Department has the same issue as Public Works with the location of the current building being off site there is currently no Fire equipment stored in the building. The ability to store items indoors keeps items in better condition and also allows for better access in any type of weather. The parking lot at city hall is scheduled for replacement in 2026, removing the building prior to construction is recommended to allow for expansion of existing parking or the potential of necessary additional space for stormwater treatment which will be required by the Watershed District for any future impermeable surface addition or alteration. Removal of the building will improve the City Hall grounds creating a more open space environment for the new playground and tennis/pickle ball facility which will help support the significant seasonal events. We have included the estimates from 4 vendors, Lester Buildings, Morton Buildings, Sherman Buildings & Structural Buildings. Not all vendors were able to quote the same size building and still remain within our required budget amount. Issue: Should the City Council approve the construction of new cold storage building behind the Fire/Public Works Building with the condition of dismantling and removing of the current cold storage building and foundation in the City Hall parking lot? Proposal Details: Contract with Sherman Buildings to construct a 50’ x 96’ building at the Fire/PW facility for cold storage of both fire and public works items. Once approved City staff will prepare site to allow the contractor to start as soon as possible. Once completed, put out an RFP to remove the current building from the city hall parking lot to allow increasing the parking lot size or other required future needs of the City. Fiscal Impact: The project is in the CIP and costs are close to budget estimates. The CIP fund will remain positive with the approval of this project. We recommend using Sherman Buildings in the amount of $161,139.67. Options: (1) Approve 50’x98’ building from Sherman buildings in the amount of $161,139.67. (2) Approve a different size building (3) Decline replacing building Recommendation: Option (1). 2'3'5'6'6' 36" Steel 12' x 14'16' x 14'36" SteelThermal90/115 MPH Windload 90/115 MPH Windload Thermal Door Door Ins Overhead Door Ins Overhead Door 36" Steel 16' x 14' Thermal Door 90/115 MPH Windload Ins Overhead Door 6'6'5'5'6'6' 12" Boxed Soffit & Fascia Overhangs on 2 Sides 24" Boxed Soffit & Fascia Overhangs on 2 Sides City of Scandia Fire Dept. 50' x 96' x 16' Ceiling 8' o.c. eave posts 8' o.c. Trusses