09.d3 2024 Street Improvement Project - Contractor's Request for Payment No 6 Final
14727 209 th St. N., Scandia, Minnesota 55073
Phone (651) 433 -2274 Fax (651) 433 -5112 https://www.cityofscandia.com
November 19, 2024
Honorable Mayor and City Council
City of Scandia
14727 209th Street N.
Scandia, MN 55073-8503
Re: Contractor’s Request for Payment No. 6 & Final
2024 Street Improvement Project
Dear Mayor and Council:
Enclosed please find Contractor’s Request for Payment No. 6 & Final, for the 2024 Street
Improvement Project. We recommend the council approve the Contractor’s Request for Payment
No. 6 & Final and pay $54,749.65 to Asphalt Surface Technologies Corporation. This amount
includes work required to complete shouldering and driveway tie-ins for phase 2 and 3 roads, as
well as final restoration. This request includes withholding 0% for retainage.
Please call me at (651) 308-1491 if there are any questions or concerns regarding this
Contractor’s Payment request.
Sincerely,
Isiah Bubany, P.E.
Project Engineer
Enclosures: Contractor’s Request for Payment No. 6 & Final, IC 134’s, Consent of Surety, and
Lien Waivers
Contractor's Application for Payment
Owner's Project No.:
Engineer's Project No.:
Agency's Project No.:
6 & Final From 08/31/24 to 11/13/24
A C D E F F1 F2 G H I J K L
Item Quantity Units
Unit Price
($)
Value of Bid Item
(C X E)
($)
Quantity Previous
Estimate
Value Previous
Estimate
Estimated
Quantity
Incorporated in
the Work
Value of Work
Completed to Date
(E X G)
($)
1 1.00 LUMP SUM 112,000.00 112,000.00 1.00 112,000.00 1.00 112,000.00 112,000.00 100% -
2 1.00 LUMP SUM 3,300.00 3,300.00 1.00 3,300.00 1.00 3,300.00 3,300.00 100% -
3 1.00 LUMP SUM 5,000.00 5,000.00 3.00 15,000.00 3.00 15,000.00 15,000.00 300% (10,000.00)
4 8.00 EACH 990.00 7,920.00 12.00 11,880.00 12.00 11,880.00 11,880.00 150% (3,960.00)
5 1.00 EACH 660.00 660.00 1.00 660.00 1.00 660.00 660.00 100% -
6 10.00 EACH 302.50 3,025.00 - - - - - 3,025.00
7 4.00 EACH 440.00 1,760.00 4.00 1,760.00 4.00 1,760.00 1,760.00 100% -
8 3.00 EACH 209.00 627.00 3.00 627.00 3.00 627.00 627.00 100% -
9 2.00 EACH 195.80 391.60 2.00 391.60 2.00 391.60 391.60 100% -
10 40.00 LIN FT 12.10 484.00 40.00 484.00 40.00 484.00 484.00 100% -
11 627.00 LIN FT 11.88 7,448.76 695.00 8,256.60 695.00 8,256.60 8,256.60 111% (807.84)
12 1.00 EACH 242.00 242.00 1.00 242.00 1.00 242.00 242.00 100% -
13 2.00 EACH 286.00 572.00 2.00 572.00 2.00 572.00 572.00 100% -
14 35.00 EACH 170.50 5,967.50 35.00 5,967.50 35.00 5,967.50 5,967.50 100% -
15 2.00 EACH 550.00 1,100.00 2.00 1,100.00 2.00 1,100.00 1,100.00 100% -
16 200.00 SQ YD 13.22 2,644.00 322.00 4,256.84 322.00 4,256.84 4,256.84 161% (1,612.84)
17 232.00 LIN FT 3.50 812.00 252.00 882.00 252.00 882.00 882.00 109% (70.00)
18 71,260.00 SQ YD 0.84 59,858.40 71,260.00 59,858.40 71,260.00 59,858.40 59,858.40 100% -
19 727.00 LIN FT 3.08 2,239.16 1,248.00 3,843.84 1,248.00 3,843.84 3,843.84 172% (1,604.68)
20 190.00 LIN FT 5.50 1,045.00 195.00 1,072.50 195.00 1,072.50 1,072.50 103% (27.50)
21 1,405.00 LIN FT 16.80 23,604.00 1,713.00 28,778.40 1,713.00 28,778.40 28,778.40 122% (5,174.40)
22 640.00 CU YD 22.00 14,080.00 64.00 1,408.00 64.00 1,408.00 1,408.00 10% 12,672.00
23 2,600.00 CU YD 16.50 42,900.00 1,146.20 18,912.30 1,146.20 18,912.30 18,912.30 44% 23,987.70
24 770.00 CU YD 31.90 24,563.00 205.00 6,539.50 205.00 6,539.50 6,539.50 27% 18,023.50
25 7,130.00 SQ YD 1.10 7,843.00 3,111.00 3,422.10 3,111.00 3,422.10 3,422.10 44% 4,420.90
26 2,300.00 CU YD 24.64 56,672.00 2,868.19 70,672.20 2,868.19 70,672.20 70,672.20 125% (14,000.20)
27 560.00 TON 26.07 14,599.20 1,739.32 45,344.07 1,739.32 45,344.07 45,344.07 311% (30,744.87)
28 71,260.00 SQ YD 1.10 78,386.00 71,260.00 78,386.00 71,260.00 78,386.00 78,386.00 100% -
29 3,180.00 TON 31.46 100,042.80 1,977.76 62,220.24 2,043.31 64,282.54 64,282.54 64% 35,760.26
30 20.00 TON 44.80 896.00 4.69 210.11 20.14 902.27 902.27 101% (6.27)
31 50.00 TON 44.80 2,240.00 48.81 2,186.69 48.81 2,186.69 2,186.69 98% 53.31
32 390.00 TON 35.00 13,650.00 91.42 3,199.70 91.42 3,199.70 3,199.70 23% 10,450.30
33 540.00 SQ YD 49.50 26,730.00 323.32 16,004.50 323.32 16,004.50 16,004.50 60% 10,725.50
34 6,900.00 TON 88.11 607,959.00 6,240.48 549,848.69 6,240.48 549,848.69 549,848.69 90% 58,110.31
35 11,500.00 TON 86.26 991,990.00 10,026.95 864,924.71 10,026.95 864,924.71 864,924.71 87% 127,065.29
36 5,590.00 GAL 3.30 18,447.00 3,036.00 10,018.80 3,036.00 10,018.80 10,018.80 54% 8,428.20
37 200.00 SQ YD 44.00 8,800.00 238.89 10,511.11 238.89 10,511.11 10,511.11 119% (1,711.11)
38 3.00 EACH 1,727.00 5,181.00 3.00 5,181.00 3.00 5,181.00 5,181.00 100% -
39 398.00 LIN FT 50.60 20,138.80 380.00 19,228.00 380.00 19,228.00 19,228.00 95% 910.80
40 24.00 EACH 467.50 11,220.00 22.00 10,285.00 22.00 10,285.00 10,285.00 92% 935.00
41 274.00 LIN FT 67.10 18,385.40 344.00 23,082.40 344.00 23,082.40 23,082.40 126% (4,697.00)
42 15.00 EACH 1,382.70 20,740.50 17.00 23,505.90 17.00 23,505.90 23,505.90 113% (2,765.40)
43 1.00 EACH 1,457.50 1,457.50 1.00 1,457.50 1.00 1,457.50 1,457.50 100% -
44 45.00 EACH 71.50 3,217.50 45.00 3,217.50 45.00 3,217.50 3,217.50 100% -
45 1.00 EACH 1,980.00 1,980.00 1.00 1,980.00 1.00 1,980.00 1,980.00 100% -
46 1.00 EACH 3,245.00 3,245.00 1.00 3,245.00 1.00 3,245.00 3,245.00 100% -
47 1.00 EACH 5,313.00 5,313.00 1.00 5,313.00 1.00 5,313.00 5,313.00 100% -
48 1.00 EACH 605.00 605.00 1.00 605.00 1.00 605.00 605.00 100% -
49 76.00 EACH 220.00 16,720.00 76.00 16,720.00 76.00 16,720.00 16,720.00 100% -
Contract Information
Bid Item
No.
CLEARING AND GRUBBING
REMOVE TREE
SALVAGE PIPE CULVERT
REMOVE STORM PIPE/CULVERT
REMOVE TRASH GUARD
REMOVE CONCRETE APRON
REMOVE METAL APRON
REMOVE STUMP
SALVAGE AND REINSTALL MAILBOX
SALVAGE AND REINSTALL DELINEATOR
Application Date:Application Period:Application No.:
Engineer:
Contractor:
Project:
Contract:
Previous Estimate
11/13/24
B
BASE BID
% of
Value of
Item
(J / F)
(%)
Balance to Finish
(F - J)
($)
MOBILIZATION
TRAFFIC CONTROL
Description
Work Completed
Materials Currently
Stored (not in G)
($)
Work Completed
and Materials
Stored to Date
(H + I)
($)
Progress Estimate - Unit Price Work
City of Scandia
Bolton & Menk, Inc.
Asphalt Surface Technologies Corporation a/k/a ASTECH Corp.
2024 Street Improvement Project
Owner:
0N1.131876
GEOTEXTILE FABRIC, TYPE V NON-WOVEN
HAUL AWAY EXCESS RECLAIM MATERIAL TO CITY GRAVEL
AGGREGATE BASE, CLASS 5
TOLERANCE RECLAIM (P)
AGGREGATE SHOULDERING, CLASS 2 LIMESTONE
SALVAGE CASTING
SALVAGE METAL APRON
TELEVISE STORM PIPE
DITCH GRADING
SALVAGE AND REINSTALL RECLAIM MATERIAL (P)
SUBGRADE EXCAVATION (EV)
COMMON EXCAVATION (LV)
REMOVE DRAINAGE STRUCTURE
REMOVE BITUMINOUS PAVEMENT - DRIVEWAY
SAW CUT BITUMINOUS PAVEMENT - FULL DEPTH
RECLAIM BITUMINOUS PAVEMENT (8" THICK) (P)
CLEAN PIPE CULVERT
TYPE SP 12.5 LOWER WEARING COURSE MIXTURE (3,C)
BITUMINOUS MATERIAL FOR TACK COAT
TYPE SP 9.5 WEARING COURSE MIXTURE (3,B) - DRIVEWAY
CONNECT TO EXISTING STORM SEWER
15" CMP, CULVERT (DRIVEWAY)
AGGREGATE SURFACING, 3/4" MINUS LIMESTONE -
AGGREGATE SURFACING, 1/2" MINUS TRAP ROCK -
AGGREGATE SURFACING CLASS 5
BITUMINOUS PATCH SPECIAL
TYPE SP 9.5 UPPER WEARING COURSE MIXTURE (3,C)
27" DIA STORM SEWER CBBH, INCL NEW CSTG (DETAIL H)
4' DIA STORM SEWER MH, INCL SALVAGED CSTG (STO-3)
5' DIA STORM SEWER CBMH, INCL SALVAGED CSTG (DETAIL
ADJUST SALVAGED SAN MH CSTG, INCL HDPE RINGS
CULVERT END PROTECTION
15" CMP, APRON (DRIVEWAY)
15" RC PIPE (CLASS 5)
15" RC PIPE APRON
21" RC PIPE APRON
STRUCTURE MARKER
Unit Price
EJCDC C-620 Contractor's Application for Payment
(c) 2018 National Society of Professional Engineers for EJCDC. All rights reserved.2 of 4
Contractor's Application for Payment
Owner's Project No.:
Engineer's Project No.:
Agency's Project No.:
6 & Final From 08/31/24 to 11/13/24
A C D E F F1 F2 G H I J K L
Item Quantity Units
Unit Price
($)
Value of Bid Item
(C X E)
($)
Quantity Previous
Estimate
Value Previous
Estimate
Estimated
Quantity
Incorporated in
the Work
Value of Work
Completed to Date
(E X G)
($)
Contract Information
Bid Item
No.
Application Date:Application Period:Application No.:
Engineer:
Contractor:
Project:
Contract:
Previous Estimate
11/13/24
B
% of
Value of
Item
(J / F)
(%)
Balance to Finish
(F - J)
($)Description
Work Completed
Materials Currently
Stored (not in G)
($)
Work Completed
and Materials
Stored to Date
(H + I)
($)
Progress Estimate - Unit Price Work
City of Scandia
Bolton & Menk, Inc.
Asphalt Surface Technologies Corporation a/k/a ASTECH Corp.
2024 Street Improvement Project
Owner:
0N1.131876
50 2.00 EACH 200.00 400.00 1.00 200.00 1.00 200.00 200.00 50% 200.00
51 400.00 LIN FT 4.95 1,980.00 1,450.55 7,180.20 1,450.55 7,180.20 7,180.20 363% (5,200.20)
52 10.00 CU YD 115.50 1,155.00 19.00 2,194.50 53.42 6,169.50 6,169.50 534% (5,014.50)
53 20.00 CU YD 115.50 2,310.00 12.00 1,386.00 12.00 1,386.00 1,386.00 60% 924.00
54 770.00 CU YD 44.00 33,880.00 263.00 11,572.00 263.00 11,572.00 11,572.00 34% 22,308.00
55 950.00 SQ YD 4.40 4,180.00 674.00 2,965.60 674.00 2,965.60 2,965.60 71% 1,214.40
56 3,670.00 SQ YD 4.40 16,148.00 3,830.00 16,852.00 3,830.00 16,852.00 16,852.00 104% (704.00)
57 19,500.00 LIN FT 0.82 15,990.00 19,500.00 15,990.00 19,240.00 15,776.80 15,776.80 99% 213.20
2,434,745.12 2,176,902.00 2,183,418.26 - 251,326.86
58 1.00 LUMP SUM 6,000.00 6,000.00 1.00 6,000.00 1.00 6,000.00 6,000.00 100% -
6,000.00 6,000.00 6,000.00 - -
2,440,745.12$ 2,182,902.00$ 2,189,418.26$ -$ 2,189,418.26$ 90%251,326.86$
59 1.00 EA 209.00 209.00 1.00 209.00 1.00 209.00 209.00 100% -
60 184.00 LF 11.88 2,185.92 184.00 2,185.92 184.00 2,185.92 2,185.92 100% -
61 8.00 EA 170.50 1,364.00 8.00 1,364.00 8.00 1,364.00 1,364.00 100% -
62 252.00 LF 3.50 882.00 166.00 581.00 166.00 581.00 581.00 66% 301.00
63 7,940.00 SY 0.84 6,669.60 7,940.00 6,669.60 7,940.00 6,669.60 6,669.60 100% -
64 214.00 LF 3.08 659.12 214.00 659.12 214.00 659.12 659.12 100% -
65 85.00 LF 16.80 1,428.00 94.00 1,579.20 94.00 1,579.20 1,579.20 111% (151.20)
66 290.00 CY 16.50 4,785.00 45.00 742.50 45.00 742.50 742.50 16% 4,042.50
67 800.00 SY 1.10 880.00 135.00 148.50 135.00 148.50 148.50 17% 731.50
68 350.00 CY 24.64 8,624.00 45.00 1,108.80 45.00 1,108.80 1,108.80 13% 7,515.20
69 7,940.00 SY 1.10 8,734.00 7,940.00 8,734.00 7,940.00 8,734.00 8,734.00 100% -
70 390.00 TN 31.46 12,269.40 249.88 7,861.22 249.88 7,861.22 7,861.22 64% 4,408.18
71 20.00 TN 44.80 896.00 31.75 1,422.40 31.75 1,422.40 1,422.40 159% (526.40)
72 40.00 TN 35.00 1,400.00 10.85 379.75 10.85 379.75 379.75 27% 1,020.25
73 60.00 SY 49.50 2,970.00 - - - - - 2,970.00
74 770.00 TN 88.11 67,844.70 832.53 73,354.22 832.53 73,354.22 73,354.22 108% (5,509.52)
75 1,280.00 TN 86.26 110,412.80 1,142.74 98,572.75 1,142.74 98,572.75 98,572.75 89% 11,840.05
76 630.00 GAL 3.30 2,079.00 457.00 1,508.10 457.00 1,508.10 1,508.10 73% 570.90
77 34.00 LF 46.20 1,570.80 34.00 1,570.80 34.00 1,570.80 1,570.80 100% -
78 2.00 EA 302.50 605.00 2.00 605.00 2.00 605.00 605.00 100% -
79 30.00 LF 50.60 1,518.00 30.00 1,518.00 30.00 1,518.00 1,518.00 100% -
80 2.00 EA 467.50 935.00 2.00 935.00 2.00 935.00 935.00 100% -
81 64.00 EA 67.10 4,294.40 64.00 4,294.40 64.00 4,294.40 4,294.40 100% -
82 4.00 EA 1,382.70 5,530.80 4.00 5,530.80 4.00 5,530.80 5,530.80 100% -
83 9.00 EA 71.50 643.50 9.00 643.50 9.00 643.50 643.50 100% -
84 1.00 EA 665.50 665.50 1.00 665.50 1.00 665.50 665.50 100% -
85 15.00 EA 220.00 3,300.00 15.00 3,300.00 15.00 3,300.00 3,300.00 100% -
86 1.00 EA 200.00 200.00 1.00 200.00 1.00 200.00 200.00 100% -
87 70.00 CY 44.00 3,080.00 33.00 1,452.00 33.00 1,452.00 1,452.00 47% 1,628.00
88 300.00 SY 4.40 1,320.00 171.00 752.40 171.00 752.40 752.40 57% 567.60
89 90.00 SY 4.40 396.00 50.00 220.00 50.00 220.00 220.00 56% 176.00
TURF RESTORATION, SEED MIXTURE (25-131), AND BLANKET
TURF RESTORATION, SEED MIXTURE (35-241), AND BLANKET
4" DOUBLE YELLOW LINE, MULTI COMP
CLEARING AND GRUBBING
SALVAGE CASTING
STORM DRAIN INLET PROTECTION
BIOLOG
RANDOM RIP RAP CLASS II
RANDOM RIP RAP CLASS III
COMMON TOPSOIL BORROW (LV)
ALTERNATE 1
BASE BID TOTAL
ALTERNATE 1 TOTAL
CHANGE ORDER 1
BASE BID + ALTERNATE 1 TOTAL
DITCH GRADING
SUBGRADE EXCAVATION
GEOTEXTILE FABRIC, TYPE V NON-WOVEN
HAUL AWAY EXCESS RECLAIMED MATERIAL TO CITY GRAVEL
TOLERANCE RECLAIM (P)
REMOVE STORM PIPE/CULVERT
REMOVE METAL APRON
SAW CUT BITUMINOUS PAVEMENT - FULL DEPTH
RECLAIM BITUMINOUS PAVEMENT (8" THICK) (P)
CLEAN PIPE CULVERT
TYPE SP 12.5 LOWER WEARING COURSE MIXTURE (3,C)
BITUMINOUS MATERIAL FOR TACK COAT
12" CMP, CULVERT
12" CMP, APRON
15" CMP, CULVERT (DRIVEWAY)
AGGREGATE SHOULDERING, CLASS 2 LIMESTONE
AGGREGATE SURFACING, 1/2" MINUS TRAP ROCK -
AGGREGATE SURFACING, CLASS 5
BITUMINOUS PATCH SPECIAL
TYPE SP 9.5 UPPER WEARING COURSE MIXTURE (3,C)
CULVERT END PROTECTION
STORM DRAIN INLET PROTECTION
COMMON TOPSOIL BORROW (LV)
TURF RESTORATION, SEED MIXTURE (25-131), AND BLANKET
TURF RESTORATION, SEED MIXTURE (35-241), AND BLANKET
15" CMP, APRON (DRIVEWAY)
15" RC PIPE (CLASS 5)
15" RC PIPE APRON
STRUCTURE MARKER
ADJUST SALVAGED STRM CB CSTG, INCL HDPE RINGS
Unit Price
EJCDC C-620 Contractor's Application for Payment
(c) 2018 National Society of Professional Engineers for EJCDC. All rights reserved.3 of 4
Contractor's Application for Payment
Owner's Project No.:
Engineer's Project No.:
Agency's Project No.:
6 & Final From 08/31/24 to 11/13/24
A C D E F F1 F2 G H I J K L
Item Quantity Units
Unit Price
($)
Value of Bid Item
(C X E)
($)
Quantity Previous
Estimate
Value Previous
Estimate
Estimated
Quantity
Incorporated in
the Work
Value of Work
Completed to Date
(E X G)
($)
Contract Information
Bid Item
No.
Application Date:Application Period:Application No.:
Engineer:
Contractor:
Project:
Contract:
Previous Estimate
11/13/24
B
% of
Value of
Item
(J / F)
(%)
Balance to Finish
(F - J)
($)Description
Work Completed
Materials Currently
Stored (not in G)
($)
Work Completed
and Materials
Stored to Date
(H + I)
($)
Progress Estimate - Unit Price Work
City of Scandia
Bolton & Menk, Inc.
Asphalt Surface Technologies Corporation a/k/a ASTECH Corp.
2024 Street Improvement Project
Owner:
0N1.131876
258,351.54$ 228,767.48$ 228,767.48$ -$ 228,767.48$ 89%29,584.06$
2,699,096.66$ 2,411,669.48$ 2,418,185.74$ -$ 2,418,185.74$ 90%280,910.92$ PROJECT TOTAL
CHANGE ORDER 1 TOTAL
BASE BID, ALTERNATE 1 + CHANGE ORDER 1
Unit Price
EJCDC C-620 Contractor's Application for Payment
(c) 2018 National Society of Professional Engineers for EJCDC. All rights reserved.4 of 4
Travelers Casualty and Surety Company of America
Travelers Casualty and Surety Company
St. Paul Fire and Marine Insurance Company
State of Connecticut
By: ________________________________________________
Robert L. Raney, Senior Vice President City of Hartford ss.
On this the 21st day of April, 2021, before me personally appeared Robert L. Raney, who acknowledged himself to be the Senior
Vice President of each of the Companies, and that he, as such, being authorized so to do, executed the foregoing instrument for the
purposes therein contained by signing on behalf of said Companies by himself as a duly authorized officer.
IN WITNESS WHEREOF, I hereunto set my hand and official seal.
My Commission expires the 30th day of June, 2026 ______________________________________________
Anna P. Nowik, Notary Public
This Power of Attorney is granted under and by the authority of the following resolutions adopted by the Boards of Directors of each of
the Companies, which resolutions are now in full force and effect, reading as follows:
I, Kevin E. Hughes, the undersigned, Assistant Secretary of each of the Companies, do hereby certify that the above and foregoing is a
true and correct copy of the Power of Attorney executed by said Companies, which remains in full force and effect.
Dated this day of , .
________________________________________
Kevin E. Hughes, Assistant Secretary
To verify the authenticity of this Power of Attorney, please call us at 1-800-421-3880.
Please refer to the above-named Attorney(s)-in-Fact and the details of the bond to which this Power of Attorney is attached.
RESOLVED, that the Chairman, the President, any Vice Chairman, any Executive Vice President, any Senior Vice President, any Vice
President, any Second Vice President, the Treasurer, any Assistant Treasurer, the Corporate Secretary or any Assistant Secretary may appoint
Attorneys-in-Fact and Agents to act for and on behalf of the Company and may give such appointee such authority as his or her certificate of authority
may prescribe to sign with the Company's name and seal with the Company's seal bonds, recognizances, contracts of indemnity, and other writings
obligatory in the nature of a bond, recognizance, or conditional undertaking, and any of said officers or the Board of Directors at any time may
remove any such appointee and revoke the power given him or her; and it is
FURTHER RESOLVED, that the Chairman, the President, any Vice Chairman, any Executive Vice President, any Senior Vice President or
any Vice President may delegate all or any part of the foregoing authority to one or more officers or employees of this Company, provided
that each such delegation is in writing and a copy thereof is filed in the office of the Secretary; and it is
FURTHER RESOLVED, that any bond, recognizance, contract of indemnity, or writing obligatory in the nature of a bond, recognizance,
or conditional undertaking shall be valid and binding upon the Company when (a) signed by the President, any Vice Chairman, any Executive
Vice President, any Senior Vice President or any Vice President, any Second Vice President, the Treasurer, any Assistant Treasurer, the
Corporate Secretary or any Assistant Secretary and duly attested and sealed with the Company's seal by a Secretary or Assistant Secretary;
or (b) duly executed (under seal, if required) by one or more Attorneys-in-Fact and Agents pursuant to the power prescribed in his or her
certificate or their certificates of authority or by one or more Company officers pursuant to a written delegation of authority; and it is
FURTHER RESOLVED, that the signature of each of the following officers: President, any Executive Vice President, any Senior Vice President,
any Vice President, any Assistant Vice President, any Secretary, any Assistant Secretary, and the seal of the Company may be affixed by facsimile to
any Power of Attorney or to any certificate relating thereto appointing Resident Vice Presidents, Resident Assistant Secretaries or Attorneys-in-
Fact for purposes only of executing and attesting bonds and undertakings and other writings obligatory in the nature thereof, and any such Power of
Attorney or certificate bearing such facsimile signature or facsimile seal shall be valid and binding upon the Company and any such power so executed
and certified by such facsimile signature and facsimile seal shall be valid and binding on the Company in the future with respect to any bond or
understanding to which it is attached.
POWER OF ATTORNEY
KNOW ALL MEN BY THESE PRESENTS: That Travelers Casualty and Surety Company of America, Travelers Casualty and Surety Company, and
St. Paul Fire and Marine Insurance Company are corporations duly organized under the laws of the State of Connecticut (herein
collectively called the "Companies"), and that the Companies do hereby make, constitute and appoint of
, , their true and lawful Attorney(s)-in-Fact to sign, execute, seal and
acknowledge any and all bonds, recognizances, conditional undertakings and other writings obligatory in the nature thereof on behalf of
the Companies in their business of guaranteeing the fidelity of persons, guaranteeing the performance of contracts and executing or
guaranteeing bonds and undertakings required or permitted in any actions or proceedings allowed by law.
IN WITNESS WHEREOF, the Companies have caused this instrument to be signed, and their corporate seals to be hereto affixed, this 21st day of April,
2021.
JOHN C KLEIN
MINNEAPOLIS Minnesota
13th November 2024