09.d3 2024 Street Improvement Project - Contractor's Request for Payment No 6 Final 14727 209 th St. N., Scandia, Minnesota 55073 Phone (651) 433 -2274 Fax (651) 433 -5112 https://www.cityofscandia.com November 19, 2024 Honorable Mayor and City Council City of Scandia 14727 209th Street N. Scandia, MN 55073-8503 Re: Contractor’s Request for Payment No. 6 & Final 2024 Street Improvement Project Dear Mayor and Council: Enclosed please find Contractor’s Request for Payment No. 6 & Final, for the 2024 Street Improvement Project. We recommend the council approve the Contractor’s Request for Payment No. 6 & Final and pay $54,749.65 to Asphalt Surface Technologies Corporation. This amount includes work required to complete shouldering and driveway tie-ins for phase 2 and 3 roads, as well as final restoration. This request includes withholding 0% for retainage. Please call me at (651) 308-1491 if there are any questions or concerns regarding this Contractor’s Payment request. Sincerely, Isiah Bubany, P.E. Project Engineer Enclosures: Contractor’s Request for Payment No. 6 & Final, IC 134’s, Consent of Surety, and Lien Waivers Contractor's Application for Payment Owner's Project No.: Engineer's Project No.: Agency's Project No.: 6 & Final From 08/31/24 to 11/13/24 A C D E F F1 F2 G H I J K L Item Quantity Units Unit Price ($) Value of Bid Item (C X E) ($) Quantity Previous Estimate Value Previous Estimate Estimated Quantity Incorporated in the Work Value of Work Completed to Date (E X G) ($) 1 1.00 LUMP SUM 112,000.00 112,000.00 1.00 112,000.00 1.00 112,000.00 112,000.00 100% - 2 1.00 LUMP SUM 3,300.00 3,300.00 1.00 3,300.00 1.00 3,300.00 3,300.00 100% - 3 1.00 LUMP SUM 5,000.00 5,000.00 3.00 15,000.00 3.00 15,000.00 15,000.00 300% (10,000.00) 4 8.00 EACH 990.00 7,920.00 12.00 11,880.00 12.00 11,880.00 11,880.00 150% (3,960.00) 5 1.00 EACH 660.00 660.00 1.00 660.00 1.00 660.00 660.00 100% - 6 10.00 EACH 302.50 3,025.00 - - - - - 3,025.00 7 4.00 EACH 440.00 1,760.00 4.00 1,760.00 4.00 1,760.00 1,760.00 100% - 8 3.00 EACH 209.00 627.00 3.00 627.00 3.00 627.00 627.00 100% - 9 2.00 EACH 195.80 391.60 2.00 391.60 2.00 391.60 391.60 100% - 10 40.00 LIN FT 12.10 484.00 40.00 484.00 40.00 484.00 484.00 100% - 11 627.00 LIN FT 11.88 7,448.76 695.00 8,256.60 695.00 8,256.60 8,256.60 111% (807.84) 12 1.00 EACH 242.00 242.00 1.00 242.00 1.00 242.00 242.00 100% - 13 2.00 EACH 286.00 572.00 2.00 572.00 2.00 572.00 572.00 100% - 14 35.00 EACH 170.50 5,967.50 35.00 5,967.50 35.00 5,967.50 5,967.50 100% - 15 2.00 EACH 550.00 1,100.00 2.00 1,100.00 2.00 1,100.00 1,100.00 100% - 16 200.00 SQ YD 13.22 2,644.00 322.00 4,256.84 322.00 4,256.84 4,256.84 161% (1,612.84) 17 232.00 LIN FT 3.50 812.00 252.00 882.00 252.00 882.00 882.00 109% (70.00) 18 71,260.00 SQ YD 0.84 59,858.40 71,260.00 59,858.40 71,260.00 59,858.40 59,858.40 100% - 19 727.00 LIN FT 3.08 2,239.16 1,248.00 3,843.84 1,248.00 3,843.84 3,843.84 172% (1,604.68) 20 190.00 LIN FT 5.50 1,045.00 195.00 1,072.50 195.00 1,072.50 1,072.50 103% (27.50) 21 1,405.00 LIN FT 16.80 23,604.00 1,713.00 28,778.40 1,713.00 28,778.40 28,778.40 122% (5,174.40) 22 640.00 CU YD 22.00 14,080.00 64.00 1,408.00 64.00 1,408.00 1,408.00 10% 12,672.00 23 2,600.00 CU YD 16.50 42,900.00 1,146.20 18,912.30 1,146.20 18,912.30 18,912.30 44% 23,987.70 24 770.00 CU YD 31.90 24,563.00 205.00 6,539.50 205.00 6,539.50 6,539.50 27% 18,023.50 25 7,130.00 SQ YD 1.10 7,843.00 3,111.00 3,422.10 3,111.00 3,422.10 3,422.10 44% 4,420.90 26 2,300.00 CU YD 24.64 56,672.00 2,868.19 70,672.20 2,868.19 70,672.20 70,672.20 125% (14,000.20) 27 560.00 TON 26.07 14,599.20 1,739.32 45,344.07 1,739.32 45,344.07 45,344.07 311% (30,744.87) 28 71,260.00 SQ YD 1.10 78,386.00 71,260.00 78,386.00 71,260.00 78,386.00 78,386.00 100% - 29 3,180.00 TON 31.46 100,042.80 1,977.76 62,220.24 2,043.31 64,282.54 64,282.54 64% 35,760.26 30 20.00 TON 44.80 896.00 4.69 210.11 20.14 902.27 902.27 101% (6.27) 31 50.00 TON 44.80 2,240.00 48.81 2,186.69 48.81 2,186.69 2,186.69 98% 53.31 32 390.00 TON 35.00 13,650.00 91.42 3,199.70 91.42 3,199.70 3,199.70 23% 10,450.30 33 540.00 SQ YD 49.50 26,730.00 323.32 16,004.50 323.32 16,004.50 16,004.50 60% 10,725.50 34 6,900.00 TON 88.11 607,959.00 6,240.48 549,848.69 6,240.48 549,848.69 549,848.69 90% 58,110.31 35 11,500.00 TON 86.26 991,990.00 10,026.95 864,924.71 10,026.95 864,924.71 864,924.71 87% 127,065.29 36 5,590.00 GAL 3.30 18,447.00 3,036.00 10,018.80 3,036.00 10,018.80 10,018.80 54% 8,428.20 37 200.00 SQ YD 44.00 8,800.00 238.89 10,511.11 238.89 10,511.11 10,511.11 119% (1,711.11) 38 3.00 EACH 1,727.00 5,181.00 3.00 5,181.00 3.00 5,181.00 5,181.00 100% - 39 398.00 LIN FT 50.60 20,138.80 380.00 19,228.00 380.00 19,228.00 19,228.00 95% 910.80 40 24.00 EACH 467.50 11,220.00 22.00 10,285.00 22.00 10,285.00 10,285.00 92% 935.00 41 274.00 LIN FT 67.10 18,385.40 344.00 23,082.40 344.00 23,082.40 23,082.40 126% (4,697.00) 42 15.00 EACH 1,382.70 20,740.50 17.00 23,505.90 17.00 23,505.90 23,505.90 113% (2,765.40) 43 1.00 EACH 1,457.50 1,457.50 1.00 1,457.50 1.00 1,457.50 1,457.50 100% - 44 45.00 EACH 71.50 3,217.50 45.00 3,217.50 45.00 3,217.50 3,217.50 100% - 45 1.00 EACH 1,980.00 1,980.00 1.00 1,980.00 1.00 1,980.00 1,980.00 100% - 46 1.00 EACH 3,245.00 3,245.00 1.00 3,245.00 1.00 3,245.00 3,245.00 100% - 47 1.00 EACH 5,313.00 5,313.00 1.00 5,313.00 1.00 5,313.00 5,313.00 100% - 48 1.00 EACH 605.00 605.00 1.00 605.00 1.00 605.00 605.00 100% - 49 76.00 EACH 220.00 16,720.00 76.00 16,720.00 76.00 16,720.00 16,720.00 100% - Contract Information Bid Item No. CLEARING AND GRUBBING REMOVE TREE SALVAGE PIPE CULVERT REMOVE STORM PIPE/CULVERT REMOVE TRASH GUARD REMOVE CONCRETE APRON REMOVE METAL APRON REMOVE STUMP SALVAGE AND REINSTALL MAILBOX SALVAGE AND REINSTALL DELINEATOR Application Date:Application Period:Application No.: Engineer: Contractor: Project: Contract: Previous Estimate 11/13/24 B BASE BID % of Value of Item (J / F) (%) Balance to Finish (F - J) ($) MOBILIZATION TRAFFIC CONTROL Description Work Completed Materials Currently Stored (not in G) ($) Work Completed and Materials Stored to Date (H + I) ($) Progress Estimate - Unit Price Work City of Scandia Bolton & Menk, Inc. Asphalt Surface Technologies Corporation a/k/a ASTECH Corp. 2024 Street Improvement Project Owner: 0N1.131876 GEOTEXTILE FABRIC, TYPE V NON-WOVEN HAUL AWAY EXCESS RECLAIM MATERIAL TO CITY GRAVEL AGGREGATE BASE, CLASS 5 TOLERANCE RECLAIM (P) AGGREGATE SHOULDERING, CLASS 2 LIMESTONE SALVAGE CASTING SALVAGE METAL APRON TELEVISE STORM PIPE DITCH GRADING SALVAGE AND REINSTALL RECLAIM MATERIAL (P) SUBGRADE EXCAVATION (EV) COMMON EXCAVATION (LV) REMOVE DRAINAGE STRUCTURE REMOVE BITUMINOUS PAVEMENT - DRIVEWAY SAW CUT BITUMINOUS PAVEMENT - FULL DEPTH RECLAIM BITUMINOUS PAVEMENT (8" THICK) (P) CLEAN PIPE CULVERT TYPE SP 12.5 LOWER WEARING COURSE MIXTURE (3,C) BITUMINOUS MATERIAL FOR TACK COAT TYPE SP 9.5 WEARING COURSE MIXTURE (3,B) - DRIVEWAY CONNECT TO EXISTING STORM SEWER 15" CMP, CULVERT (DRIVEWAY) AGGREGATE SURFACING, 3/4" MINUS LIMESTONE - AGGREGATE SURFACING, 1/2" MINUS TRAP ROCK - AGGREGATE SURFACING CLASS 5 BITUMINOUS PATCH SPECIAL TYPE SP 9.5 UPPER WEARING COURSE MIXTURE (3,C) 27" DIA STORM SEWER CBBH, INCL NEW CSTG (DETAIL H) 4' DIA STORM SEWER MH, INCL SALVAGED CSTG (STO-3) 5' DIA STORM SEWER CBMH, INCL SALVAGED CSTG (DETAIL ADJUST SALVAGED SAN MH CSTG, INCL HDPE RINGS CULVERT END PROTECTION 15" CMP, APRON (DRIVEWAY) 15" RC PIPE (CLASS 5) 15" RC PIPE APRON 21" RC PIPE APRON STRUCTURE MARKER Unit Price EJCDC C-620 Contractor's Application for Payment (c) 2018 National Society of Professional Engineers for EJCDC. All rights reserved.2 of 4 Contractor's Application for Payment Owner's Project No.: Engineer's Project No.: Agency's Project No.: 6 & Final From 08/31/24 to 11/13/24 A C D E F F1 F2 G H I J K L Item Quantity Units Unit Price ($) Value of Bid Item (C X E) ($) Quantity Previous Estimate Value Previous Estimate Estimated Quantity Incorporated in the Work Value of Work Completed to Date (E X G) ($) Contract Information Bid Item No. Application Date:Application Period:Application No.: Engineer: Contractor: Project: Contract: Previous Estimate 11/13/24 B % of Value of Item (J / F) (%) Balance to Finish (F - J) ($)Description Work Completed Materials Currently Stored (not in G) ($) Work Completed and Materials Stored to Date (H + I) ($) Progress Estimate - Unit Price Work City of Scandia Bolton & Menk, Inc. Asphalt Surface Technologies Corporation a/k/a ASTECH Corp. 2024 Street Improvement Project Owner: 0N1.131876 50 2.00 EACH 200.00 400.00 1.00 200.00 1.00 200.00 200.00 50% 200.00 51 400.00 LIN FT 4.95 1,980.00 1,450.55 7,180.20 1,450.55 7,180.20 7,180.20 363% (5,200.20) 52 10.00 CU YD 115.50 1,155.00 19.00 2,194.50 53.42 6,169.50 6,169.50 534% (5,014.50) 53 20.00 CU YD 115.50 2,310.00 12.00 1,386.00 12.00 1,386.00 1,386.00 60% 924.00 54 770.00 CU YD 44.00 33,880.00 263.00 11,572.00 263.00 11,572.00 11,572.00 34% 22,308.00 55 950.00 SQ YD 4.40 4,180.00 674.00 2,965.60 674.00 2,965.60 2,965.60 71% 1,214.40 56 3,670.00 SQ YD 4.40 16,148.00 3,830.00 16,852.00 3,830.00 16,852.00 16,852.00 104% (704.00) 57 19,500.00 LIN FT 0.82 15,990.00 19,500.00 15,990.00 19,240.00 15,776.80 15,776.80 99% 213.20 2,434,745.12 2,176,902.00 2,183,418.26 - 251,326.86 58 1.00 LUMP SUM 6,000.00 6,000.00 1.00 6,000.00 1.00 6,000.00 6,000.00 100% - 6,000.00 6,000.00 6,000.00 - - 2,440,745.12$ 2,182,902.00$ 2,189,418.26$ -$ 2,189,418.26$ 90%251,326.86$ 59 1.00 EA 209.00 209.00 1.00 209.00 1.00 209.00 209.00 100% - 60 184.00 LF 11.88 2,185.92 184.00 2,185.92 184.00 2,185.92 2,185.92 100% - 61 8.00 EA 170.50 1,364.00 8.00 1,364.00 8.00 1,364.00 1,364.00 100% - 62 252.00 LF 3.50 882.00 166.00 581.00 166.00 581.00 581.00 66% 301.00 63 7,940.00 SY 0.84 6,669.60 7,940.00 6,669.60 7,940.00 6,669.60 6,669.60 100% - 64 214.00 LF 3.08 659.12 214.00 659.12 214.00 659.12 659.12 100% - 65 85.00 LF 16.80 1,428.00 94.00 1,579.20 94.00 1,579.20 1,579.20 111% (151.20) 66 290.00 CY 16.50 4,785.00 45.00 742.50 45.00 742.50 742.50 16% 4,042.50 67 800.00 SY 1.10 880.00 135.00 148.50 135.00 148.50 148.50 17% 731.50 68 350.00 CY 24.64 8,624.00 45.00 1,108.80 45.00 1,108.80 1,108.80 13% 7,515.20 69 7,940.00 SY 1.10 8,734.00 7,940.00 8,734.00 7,940.00 8,734.00 8,734.00 100% - 70 390.00 TN 31.46 12,269.40 249.88 7,861.22 249.88 7,861.22 7,861.22 64% 4,408.18 71 20.00 TN 44.80 896.00 31.75 1,422.40 31.75 1,422.40 1,422.40 159% (526.40) 72 40.00 TN 35.00 1,400.00 10.85 379.75 10.85 379.75 379.75 27% 1,020.25 73 60.00 SY 49.50 2,970.00 - - - - - 2,970.00 74 770.00 TN 88.11 67,844.70 832.53 73,354.22 832.53 73,354.22 73,354.22 108% (5,509.52) 75 1,280.00 TN 86.26 110,412.80 1,142.74 98,572.75 1,142.74 98,572.75 98,572.75 89% 11,840.05 76 630.00 GAL 3.30 2,079.00 457.00 1,508.10 457.00 1,508.10 1,508.10 73% 570.90 77 34.00 LF 46.20 1,570.80 34.00 1,570.80 34.00 1,570.80 1,570.80 100% - 78 2.00 EA 302.50 605.00 2.00 605.00 2.00 605.00 605.00 100% - 79 30.00 LF 50.60 1,518.00 30.00 1,518.00 30.00 1,518.00 1,518.00 100% - 80 2.00 EA 467.50 935.00 2.00 935.00 2.00 935.00 935.00 100% - 81 64.00 EA 67.10 4,294.40 64.00 4,294.40 64.00 4,294.40 4,294.40 100% - 82 4.00 EA 1,382.70 5,530.80 4.00 5,530.80 4.00 5,530.80 5,530.80 100% - 83 9.00 EA 71.50 643.50 9.00 643.50 9.00 643.50 643.50 100% - 84 1.00 EA 665.50 665.50 1.00 665.50 1.00 665.50 665.50 100% - 85 15.00 EA 220.00 3,300.00 15.00 3,300.00 15.00 3,300.00 3,300.00 100% - 86 1.00 EA 200.00 200.00 1.00 200.00 1.00 200.00 200.00 100% - 87 70.00 CY 44.00 3,080.00 33.00 1,452.00 33.00 1,452.00 1,452.00 47% 1,628.00 88 300.00 SY 4.40 1,320.00 171.00 752.40 171.00 752.40 752.40 57% 567.60 89 90.00 SY 4.40 396.00 50.00 220.00 50.00 220.00 220.00 56% 176.00 TURF RESTORATION, SEED MIXTURE (25-131), AND BLANKET TURF RESTORATION, SEED MIXTURE (35-241), AND BLANKET 4" DOUBLE YELLOW LINE, MULTI COMP CLEARING AND GRUBBING SALVAGE CASTING STORM DRAIN INLET PROTECTION BIOLOG RANDOM RIP RAP CLASS II RANDOM RIP RAP CLASS III COMMON TOPSOIL BORROW (LV) ALTERNATE 1 BASE BID TOTAL ALTERNATE 1 TOTAL CHANGE ORDER 1 BASE BID + ALTERNATE 1 TOTAL DITCH GRADING SUBGRADE EXCAVATION GEOTEXTILE FABRIC, TYPE V NON-WOVEN HAUL AWAY EXCESS RECLAIMED MATERIAL TO CITY GRAVEL TOLERANCE RECLAIM (P) REMOVE STORM PIPE/CULVERT REMOVE METAL APRON SAW CUT BITUMINOUS PAVEMENT - FULL DEPTH RECLAIM BITUMINOUS PAVEMENT (8" THICK) (P) CLEAN PIPE CULVERT TYPE SP 12.5 LOWER WEARING COURSE MIXTURE (3,C) BITUMINOUS MATERIAL FOR TACK COAT 12" CMP, CULVERT 12" CMP, APRON 15" CMP, CULVERT (DRIVEWAY) AGGREGATE SHOULDERING, CLASS 2 LIMESTONE AGGREGATE SURFACING, 1/2" MINUS TRAP ROCK - AGGREGATE SURFACING, CLASS 5 BITUMINOUS PATCH SPECIAL TYPE SP 9.5 UPPER WEARING COURSE MIXTURE (3,C) CULVERT END PROTECTION STORM DRAIN INLET PROTECTION COMMON TOPSOIL BORROW (LV) TURF RESTORATION, SEED MIXTURE (25-131), AND BLANKET TURF RESTORATION, SEED MIXTURE (35-241), AND BLANKET 15" CMP, APRON (DRIVEWAY) 15" RC PIPE (CLASS 5) 15" RC PIPE APRON STRUCTURE MARKER ADJUST SALVAGED STRM CB CSTG, INCL HDPE RINGS Unit Price EJCDC C-620 Contractor's Application for Payment (c) 2018 National Society of Professional Engineers for EJCDC. All rights reserved.3 of 4 Contractor's Application for Payment Owner's Project No.: Engineer's Project No.: Agency's Project No.: 6 & Final From 08/31/24 to 11/13/24 A C D E F F1 F2 G H I J K L Item Quantity Units Unit Price ($) Value of Bid Item (C X E) ($) Quantity Previous Estimate Value Previous Estimate Estimated Quantity Incorporated in the Work Value of Work Completed to Date (E X G) ($) Contract Information Bid Item No. Application Date:Application Period:Application No.: Engineer: Contractor: Project: Contract: Previous Estimate 11/13/24 B % of Value of Item (J / F) (%) Balance to Finish (F - J) ($)Description Work Completed Materials Currently Stored (not in G) ($) Work Completed and Materials Stored to Date (H + I) ($) Progress Estimate - Unit Price Work City of Scandia Bolton & Menk, Inc. Asphalt Surface Technologies Corporation a/k/a ASTECH Corp. 2024 Street Improvement Project Owner: 0N1.131876 258,351.54$ 228,767.48$ 228,767.48$ -$ 228,767.48$ 89%29,584.06$ 2,699,096.66$ 2,411,669.48$ 2,418,185.74$ -$ 2,418,185.74$ 90%280,910.92$ PROJECT TOTAL CHANGE ORDER 1 TOTAL BASE BID, ALTERNATE 1 + CHANGE ORDER 1 Unit Price EJCDC C-620 Contractor's Application for Payment (c) 2018 National Society of Professional Engineers for EJCDC. All rights reserved.4 of 4 Travelers Casualty and Surety Company of America Travelers Casualty and Surety Company St. Paul Fire and Marine Insurance Company State of Connecticut By: ________________________________________________ Robert L. Raney, Senior Vice President City of Hartford ss. On this the 21st day of April, 2021, before me personally appeared Robert L. Raney, who acknowledged himself to be the Senior Vice President of each of the Companies, and that he, as such, being authorized so to do, executed the foregoing instrument for the purposes therein contained by signing on behalf of said Companies by himself as a duly authorized officer. IN WITNESS WHEREOF, I hereunto set my hand and official seal. My Commission expires the 30th day of June, 2026 ______________________________________________ Anna P. Nowik, Notary Public This Power of Attorney is granted under and by the authority of the following resolutions adopted by the Boards of Directors of each of the Companies, which resolutions are now in full force and effect, reading as follows: I, Kevin E. Hughes, the undersigned, Assistant Secretary of each of the Companies, do hereby certify that the above and foregoing is a true and correct copy of the Power of Attorney executed by said Companies, which remains in full force and effect. Dated this day of , . ________________________________________ Kevin E. Hughes, Assistant Secretary To verify the authenticity of this Power of Attorney, please call us at 1-800-421-3880. Please refer to the above-named Attorney(s)-in-Fact and the details of the bond to which this Power of Attorney is attached. RESOLVED, that the Chairman, the President, any Vice Chairman, any Executive Vice President, any Senior Vice President, any Vice President, any Second Vice President, the Treasurer, any Assistant Treasurer, the Corporate Secretary or any Assistant Secretary may appoint Attorneys-in-Fact and Agents to act for and on behalf of the Company and may give such appointee such authority as his or her certificate of authority may prescribe to sign with the Company's name and seal with the Company's seal bonds, recognizances, contracts of indemnity, and other writings obligatory in the nature of a bond, recognizance, or conditional undertaking, and any of said officers or the Board of Directors at any time may remove any such appointee and revoke the power given him or her; and it is FURTHER RESOLVED, that the Chairman, the President, any Vice Chairman, any Executive Vice President, any Senior Vice President or any Vice President may delegate all or any part of the foregoing authority to one or more officers or employees of this Company, provided that each such delegation is in writing and a copy thereof is filed in the office of the Secretary; and it is FURTHER RESOLVED, that any bond, recognizance, contract of indemnity, or writing obligatory in the nature of a bond, recognizance, or conditional undertaking shall be valid and binding upon the Company when (a) signed by the President, any Vice Chairman, any Executive Vice President, any Senior Vice President or any Vice President, any Second Vice President, the Treasurer, any Assistant Treasurer, the Corporate Secretary or any Assistant Secretary and duly attested and sealed with the Company's seal by a Secretary or Assistant Secretary; or (b) duly executed (under seal, if required) by one or more Attorneys-in-Fact and Agents pursuant to the power prescribed in his or her certificate or their certificates of authority or by one or more Company officers pursuant to a written delegation of authority; and it is FURTHER RESOLVED, that the signature of each of the following officers: President, any Executive Vice President, any Senior Vice President, any Vice President, any Assistant Vice President, any Secretary, any Assistant Secretary, and the seal of the Company may be affixed by facsimile to any Power of Attorney or to any certificate relating thereto appointing Resident Vice Presidents, Resident Assistant Secretaries or Attorneys-in- Fact for purposes only of executing and attesting bonds and undertakings and other writings obligatory in the nature thereof, and any such Power of Attorney or certificate bearing such facsimile signature or facsimile seal shall be valid and binding upon the Company and any such power so executed and certified by such facsimile signature and facsimile seal shall be valid and binding on the Company in the future with respect to any bond or understanding to which it is attached. POWER OF ATTORNEY KNOW ALL MEN BY THESE PRESENTS: That Travelers Casualty and Surety Company of America, Travelers Casualty and Surety Company, and St. Paul Fire and Marine Insurance Company are corporations duly organized under the laws of the State of Connecticut (herein collectively called the "Companies"), and that the Companies do hereby make, constitute and appoint of , , their true and lawful Attorney(s)-in-Fact to sign, execute, seal and acknowledge any and all bonds, recognizances, conditional undertakings and other writings obligatory in the nature thereof on behalf of the Companies in their business of guaranteeing the fidelity of persons, guaranteeing the performance of contracts and executing or guaranteeing bonds and undertakings required or permitted in any actions or proceedings allowed by law. IN WITNESS WHEREOF, the Companies have caused this instrument to be signed, and their corporate seals to be hereto affixed, this 21st day of April, 2021. JOHN C KLEIN MINNEAPOLIS Minnesota 13th November 2024