Roads/ ROW
Public Works has ceased ROW brush mowing due to other priorities and a transmission issue with the
tractor. Tree trimming has been the focus now and will be over the next few months.
Public Works has installed No Parking signs at two locations where parked vehicles have continually
congested the roadway causing vehicle and pedestrian safety issues. The signs have been installed with
temporary bases and will be permanently installed in the Spring.
Due to the high volume of fallen trees during the spring/summer wet period and wind storms,
the accumulation of tree and brush debris behind the Public Works building will be ground into
mulch instead of burning as in years past. The brush pile mulching has been scheduled for the end of the
month as the company is able to mobilize the equipment necessary for the project.
Snow events have been minimal this year but have come at difficult times of the day or weather pattern.
The most recent plowable snow event started with mild temperatures, but was quickly followed by frigid
temperatures and light snow. Staff plowed and treated roads effectively and efficiently eliminating the
need for a return to the plow routes the following day.
Parks
Public Works full time staff have been supplementing in the task of Zamboni operation and rink
maintenance this season. The person hired for the role of Zamoni-Rink Maintenance operator has been
off nearly as much as he has been able to work. This was known before hiring the operator and was
planned for accordingly. He was the only applicant for the role of rink maintenance and has done very
well when working. This is a difficult role to fill due to the limited hours and days available to work or
people are not interested in this field of work.
Vinterfest preparations have already started and the weather is looking good for the rink to hold up for
the tournament after the brief warm up last week. Staff have been assisting the Park and Rec Committee
with preparation tasks leading up to the event.
Sewer
Public Works has been compiling data and costs over the last ten years for each system. This process has
been time consuming as documents detailing work completed prior to 2021 have been difficult to locate.
Staff Report
Date of Meeting: 1/ 16/2025
For: Mayor and City Council
From: Charles Fischer – Director of Public Works
Subject: PW - Staff Report
Most of the data collected was recovered by searching through all the invoices in the system for the last
ten years.
Buildings
The contractor building the new cold storage facility has been working on and off over the last month
between holiday breaks, other issues and cold weather. Progress has been made and hope to see a
finished building soon. The concrete floor and electrical service to the building will be installed in the
spring.
Equipment
Last month the John Deere tractor which operates the ditch mowing equipment developed a
transmission shift issue which resulted in not being able to use the lower operational gears. The tractor
is currently in Rogers at Minnesota Equipment for diagnostics and repair. Public Works is estimating the
work to be completed on the transmission will be in the $8,000-$10,000 range, unless less severe causes
are found after removing and assessing the transmission internal parts.
Request for Proposal
For
Demolition and Disposal/Removal:
Cold Storage Building located at
14727 209th St N
January 9, 2025
Section 1 – Administrative Information
1.1 Introduction
This Request for Proposal is for demolition and disposal/removal of a structure located at 14727
209th St N in Scandia, MN. This Request for Proposal (“RFP”) does not commit the City of
Scandia to enter into any agreement, to pay any expenses incurred in preparation of any
response to this RFP, or to procure or contract for any supplies, goods, or services. The City of
Scandia reserves the right, without liability to the City of Scandia, to cancel this RFP and to
reject any proposal that does not comply with this RFP or applicable administrative rules, and to
reject all responses received because of this RFP upon a finding that it is in the public interest to
do so.
1.2 Scope of Work
The City of Scandia is requesting proposals from those capable of efficiently dismantling and
disposing /removing of all structural components of the building (including metal frame and
supports), mechanical components (including natural gas heaters) electrical (including breaker
panel, outlets, and lights), and exterior components of the building (including siding, roofing,
access doors, windows and garage doors). Work also includes clean-up of all debris upon
completion of demolition and removal.
Pricing includes labor, materials, and equipment necessary to complete the scope of the project
and established on the following qualifications unless otherwise agreed upon in writing.
• Work to begin following the completion a new storage building currently under
construction and the removal of all City owned property within the building is moved to
the new building.
• Work to be completed in a single mobilization unless otherwise agreed upon
• Proposal is valid for 180 days
• Permitting and inspection work will be coordinated by the City.
• Proper site safety and security necessary to keep the public safe.
1.3 Insurance and Registration
Due prior to signing an agreement
• General Liability $1M/$2M
• Auto Insurance $1M/$2M
• Workers Compensation
• Professional Liability $1M/$2M
• Current Minnesota Licenses
1.4 Intended Schedule
Advertisement of Requests for Proposals ………………………………. January 27, 2025
Questions Due………………………………………………………………………… February 21, 2025
Proposals Due…………………………………………………………………………. February 28, 2025, by noon
Project Milestones
Notice to Proceed……………………………………………………………………. March 7, 2024
Building Demolition…………………………………………………………………. No later than July 28, 2025
Final Clean up………………………………………………………………………….. No later than August 1, 2025
1.5 Questions
Questions or requests for clarification must be submitted to mail@ci.scandia.mn.us.
1.6 Addenda
This solicitation will only be modified by documents issued as addenda by the Owner. No other
direction or comments received by Proposers, written or oral, will serve to change the
solicitation document.
1.7 Incurred Costs
The City of Scandia is not liable for any costs incurred by the proposer in the preparation of their
proposals.
1.8 Public Record
The City of Scandia will keep this RFQ , and each proposal received in response to it, together
with all documents pertaining to the award of any contract, as part of the file or record that is
open to public inspection.
1.9 Proposal Submission
To be considered for selection, Proposals must arrive via email by February 28, 2025, by NOON.