09.g Staff Report - City Administrator1
Staff Report
Date of Meeting: January 21, 2025, City Council Meeting
To: Mayor and City Council
From: Kyle Morell, City Administrator
Re: City Administrator Report
______________________________________________________________________________
Gateway Trail Project
City Engineer Ryan Goodman and I met with Nathan Moe and Kent Skaar from the Minnesota
Department of Natural Resources (DNR) on Monday, July 10, 2023. We discussed the next steps in the
work plan, including the environmental review, soil borings, and topographical survey. Ryan and the
DNR are working to complete these items before the end of the year. This group plans to meet monthly
to ensure the project stays on schedule.
Kent explained that the LCCMR funding has a hard deadline of June 30, 2027. All spending must be
completed before that date. The City plans for 2026 construction to complete the project before the grant
funding disappears. Our DNR Grant Administrator has also contacted me. LCCMR administers the
project, and the funding comes from the DNR.
I have submitted our first required update to LCCMR. I will have to file a budget amendment to
redistribute the funds we received from construction to engineering, as the money allotted for
engineering will not cover the projected cost. The City’s first reimbursement request has been processed
and received by the County and will be forwarded to the City.
Water Tower Barn Wetland Trail Project
The City’s LCCMR proposal was selected to move forward in the review process. I presented it to the
LCCMR committee on June 28. The Committee met on July 31 to determine funding amounts for all
projects. The City received $907,000 of the $998,000 it requested. The request will now be moved into
the LCCMR bill that will be presented to the Legislature for approval in this upcoming session. If
approved, we have until 2028 to complete the project.
2
Bliss Stormwater Project
The project is complete. We are awaiting the final bill.
Bliss Sewer Project
The City’s presentation to the Senate Capital Investment Committee went well. The Committee
Chairman, Senator Pappas, understood our unique situation. Senator Housley was also on the call. If a
bonding bill is considered, she will continue to push for funding in the upcoming session. Staff will
contact newly re-elected Representative Hill to affirm our desire to be included in any upcoming House
bonding bill.
Midco 2024 Big Marine Project
This project has been completed. The City has paid its $92,000 portion of the project.
Scandia City Center Study
This project is complete. The City has been billed for its 50% project share, just under the $50,000
estimate.
Street Parking within the City
We are running into issues with parking on Orwell Ave N at Old Marine Trl. N. A DNR property, which
is used to access Sand Lake, has attracted vehicles to park along Orwell Ave N. Per our current
ordinance, parking along Orwell is not permitted due to the requirement that a 200 ft clear line of site be
available, which is not possible due to a hill on Orwell. Staff will review this language and bring
suggestions to the Council at their February 5 Work Session.