8.f Public Works December reportPublic Works Activities
The following update is through the end of December 2016.
Roads and Right - Of – Way (ROW):
De-icing of roads and snow removal: Three events in December
Salt orders: 111.8 ton
ROW clearing: Nolan Ave, 230th, Meadow Brook Ave., 235th Ave., 228th
Ave., 238th Ave., Morgan, 236th off Nolan.
A temporary mailbox was installed along Parkview for one hit by a city
plow truck. Two mailboxes repaired – 1- on 236th, 1 – Olinda Ln.
A list of signs that were replaced last summer and will be for sale was
submitted to the city administrator as requested
8 trees were removed from the roads and ROW’s after the snow / wind
storm Dec. 26th
Cable guard rails were repaired at the intersection of Parkview and 199th –
a tree had fallen over them.
All Safe – completed the fire extinguisher checks for the year. Two
extinguishers in the Fire Depts. Vehicle were out of date and needed
testing and recharging – Water extinguishers
Sewer / Water:
Biosolids report completed and submitted with DMR report to MPCA
Continual monitoring of the lift station run times
Parks:
Warming House Building maintenance: light bulbs installed, new toilet,
new air filter, safety kits checked
Rink door repaired and installed
Flooding of rinks – Daily - another warm spell is coming
Zamboni rm. garage door repaired
Zamboni repairs and new blade installed
Plowed Lilleskogen Park, walks and rinks after snow falls
Rick was cross trained in the operation of the Zamboni
Visited parks with Neil on a city tour
Vinterfest signs were put up
Electrical repairs done to John Deere by Frontier Dealership – Safety switch
relay was the issue
Other:
Shop cleaning and organizing to promote efficiency
Minor repairs to equipment and equipment maintenance
Developed a list of customers that would like either the wood or the chips
from the process of ROW clearing
Researching capital purchases – 2009 John Deere mower, single axle
dump truck