09.e Public Works Staff Report
Staff Report
Date of Meeting: 4/15/2025
For: Mayor and City Council
From: Charles Fischer – Director of Public Works
Subject: PW - Staff Report
Roads/ ROW
Public Works staff wrapped up tree trimming by the end of March. The final stretch of roadway trimmed
was Kirk Ave west of Manning between 230th and 220th St. Public Works will continue to monitor Ash
trees and other hazard trees within the ROW and complete removals throughout the year.
Although we have had two light snow seasons back-to-back the extended sub-zero nights this year drove
the frost deep beneath the roadways. During the thaw cycle this spring, areas of roadways already in
sub-par conditions have been considerably affected due to the long thaw cycle. Areas which had already
displayed allegator cracking are now beginning to sink and road base material has began pushing out to
the sides of the road. Some of these road sections are within the current five-year cycle to be
reconstructed, but others are not and additional major patch work will need to be completed to
continue safe passage of vehicles. Public Works will be finalizing a list this month of areas which require
patching, but will not complete work in these areas until CIP Committee meetings have determined
which roads will fall into the five-year cycle for road reconstruction.
Parks
Public Works staff completed tree trimming at the Wayne Erickson and T-ball fields. After many years of
unattended growth, the trees outside of the play area had stretched over the fences or play areas
affecting the use of the fields. Trees were cut back to a point outside of the play area and should only
require routine pruning moving forward.
The tennis/pickleball court project is scheduled to be substantially completed by the end of May.
Punchlist items to complete are likely to run into the month of June. Opening the courts will take place
when deemed ready for play by the City Engineer and Public Works. No specific date has been set at this
time.
Tree planting in the parks will take place around the City Hall parking lot this year to replace the infested
ash trees which had been removed over the winter. Quantity and type are still being determined based
on cost and available space. There will likely not be a one-one replacement but a healthy number of
trees will be planted.
Sewer
The MPCA has added additional monitoring and restrictions to the permit associated with the Bliss
Collector system. PFAS has been an ongoing issue in the east metro and Scandia is now falling into the
area requiring additional monitoring, not only for wastewater but groundwater as well. The additional
monitoring and restrictions relate to the land application of biosolids from the tank pumping process.
After tanks are pumped the City has two options for disposal; land application or trucking the pumped
wastewater and biosolids to the Met plant in St. Paul. The MPCA is now concerned with the amount of
PFAS re-entering the ground through wastewater disposal and will be setting limits on land application
dependent upon the concentration of PFAS in the wastewater. So far, the City has not tested for PFAS in
the wastewater as there has not been a land application completed since the new regulations have gone
into effect. As of this time, there is no known sample indicating if there is any concentration of PFAS in
the wastewater treated at this facility.
Buildings
The new cold storage building is scheduled to have the floor and driveway concrete installed after road
restrictions are lifted. Public Works will be completing the rough grading in and around the building in
the interim.
Power and gas have been disconnected from the old cold storage building in preparation for the
dismantling process. Public Works will continue to move out items from the old building which can be
temporarily stored outside behind the Public Works/Fire Hall building. The majority of the items
currently in the building will be moved after the new concrete has cured long enough for safe use of
machinery within the new building. The anticipated schedule has the old building ready for dismantle in
June.
Bone Lake Tree Nursery
The tree nursery was successfully moved to the new location west of the Warming House the first week
of April. Public Works assisted in removing the pea gravel so that Tom could dismantle and move the
framework. Public Works then moved and filled the frame work with the existing gravel. Public Works
also discussed the option of having trees planted in the nursery for use in the Parks. Tom indicated there
is room for trees in the nursery and to be available for the City to plant this fall. After the bed is planted
this spring, we will know the number of potential trees available for fall installation.