06.g 4-21-2026 Engineering Updates
City of Scandia
Engineering Updates 4/21/2026
Engineering Italics = Old information
Red = Projects to be removed from report
• 2026 Street Improvement Project (197th Street)
➢ Topo survey was collected over multiple days in early August 2025.
➢ Soil Boring draft logs were received from AET on August 26, 2025.
➢ A public meeting was held for residents on September 8, 2025.
o A presentation providing background information and proposed improvements was given by City
Staff along with Bolton and Menk.
o Design aspects, construction timeline, residential impacts, and other factors were discussed at
length with property owners.
➢ Anticipated project schedule is as follows:
o Approve Plans & Specifications/Authorize Ad for Bid – April 21, 2026.
o Bid Opening – May 13, 2026.
o Consider Contract Award at City Council Meeting – May 19, 2026.
➢ A survey was sent to residents at the end of October requesting information regarding access to their properties.
The survey will help us determine working hours, completion dates, and traffic impact mitigation options for the
project.
➢ We are planning to hold a meeting for resident feedback in early January.
➢ Survey results have been received and are being reviewed.
➢ 60% Draft Plans will be completed and sent to the City Staff for review by the end of December. Upon receiving
and implementing City comments, a public meeting will be scheduled in January with residents to present the
project and receive additional feedback on the improvements.
➢ A meeting with residents is scheduled for January 26th, at 6:00pm to go over plans, construction schedule, and
traffic impacts. Feedback from residents will be received and reviewed for implementation where feasible.
➢ Based on historic burial sites along TH 95 this project has been pinged for cultural resources review to be
completed. This review is underway but will require an on-site survey once the snow has melted.
➢ The January 26th meeting discussion with residents is being reviewed for implementation options as part of the
project’s final design.
➢ Final Plans will be made available for residents in this area once they are finalized early this spring.
➢ Final Plans are anticipated to be completed and ready to distribute to residents by April 10th, 2026.
➢ Requesting approval of plans and specs to authorize advertisements for bid will take place in May 2026 to
ensure residents can submit questions and cultural resources review has been completed.
➢ An updated plan set was sent to the City for distribution the week of April 13-17th.
➢ A follow-up meeting with residents will be scheduled in the next few weeks to finalize plans
prior to the May Council Meeting.
• 2026 Scandia Trails Project
➢ Anticipated project schedule is as follows:
o Approve Plans & Specifications/Authorize Ad for Bid – February 17, 2026.
o Bid Opening – March 11, 2026.
o Consider Contract Award at City Council Meeting – March 17, 2026.
➢ Topo Survey is scheduled to be completed by October 24, 2025.
➢ Continued coordination is being had with the Scandia Heritage Alliance group and CMSCWD.
o Variances will be required from CMSCWD in order to construct the project as desired.
➢ 60% Draft Plans will be completed and sent to City Staff for review by the end of December.
➢ Additional coordination will take place with the Scandia Heritage Alliance group over the next few weeks to
complete the boardwalk design.
➢ 60% Draft Plans were sent to City Staff to review and provide comments.
➢ CMSCWD permitting for this project will be on the agenda for review at their February Board Meeting.
➢ A preconstruction meeting is being scheduled for late April.
➢ Winberg is tentatively planning on beginning construction in May.
• 2025 Street Improvement Project
➢ Anticipated project schedule is as follows:
o Approve Plans & specifications/Authorize Ad for Bid – January 21, 2025.
o Bid Opening – February 19, 2025.
o Consider Contract Award at City Council Meeting – March 18, 2025.
➢ Geotechnical report was received on December 11, 2024.
➢ Both CMSCWD and CLFLWD were contacted regarding potential “add-on” projects that could be implemented as
part of the 2025 Street Improvement Project. Neither watershed identified any potential projects within our
scope.
➢ CMSCWD will not be requiring any permits for this project. Permit application for CLFLWD will be submitted later
this month.
➢ The following permits applications have been submitted:
o Washington County right of way
o Comfort Lake Forest Lake Watershed District erosion and sediment control
o Type & Boundary (wetland delineations)
➢ Bids were opened on Wednesday, February 19th at 9:00am. Six Contractors submitted bids for the base bid and
alternate 1 for this project.
➢ The preconstruction meeting for this project has been scheduled for Tuesday, April 15th at 10:00am.
➢ Construction notices will be delivered to residents two weeks prior to the start of construction that will include
an anticipated project schedule.
➢ Construction is anticipated to begin on Monday June 9th.
➢ A preliminary schedule has been included at the end of this report for reference.
o The Contractor will begin construction once completed with the Marine on St. Croix 2025 Street
Improvement Project. This has been reflected in the schedule attached.
➢ The Contractor began reclaiming project streets on May 23rd.
➢ Storm sewer improvements began the week of May 26th.
➢ Initial roll testing and subgrade corrections began the week of June 2nd.
➢ A test roll of the corrected reclaimed base material was conducted using a fully loaded water truck supplied by
the City of Scandia on June 24th.
➢ The base layer of bituminous pavement was paved on June 30th.
➢ Core samples were taken the following day and sent to Braun for testing.
➢ Contractor’s Request for Payment No. 3 has been included as a separate agenda item.
➢ Bituminous base patching was completed on July 15th.
➢ Bituminous wear paving was completed on July 17th.
➢ Culverts were cleaned at the end of July.
➢ The final punchlist has been sent to Valley Paving. Final quantities are being discussed to get final
documentation process started for close out.
➢ The punch list still has a few restoration items remaining that must be addressed prior to project closeout. These
remaining items will need to be completed in the Spring before final closeout.
➢ We will be performing a punch list inspection in the next few weeks to determine what
items remain prior to closing out this project.
• Tii Gavo Development Phase II
➢ Watershed permit has been obtained and grading work began on Tuesday July 11th. BMI will have staff on site
for public infrastructure inspections.
➢ The bituminous base layer was paved on 8/17/2023.
➢ Aggregate shouldering was completed on 8/30/2023.
➢ Hand auger borings have been scheduled for each of the non-functioning basins along with a grain analysis and
hydrometer testing.
➢ A request to reduce the Letter of Credit for this development has been included as a separate agenda item.
➢ Plowe is currently working on the corrective design for the basins on-site, in coordination with the watershed,
and hoping to have an approved plan within the next few weeks.
➢ Corrective design has been completed and is being reviewed by the Contractor. The finalized plans will then be
sent to the CMSCWD and City for review during the week of November 11th – 15th.
➢ Corrective designs were submitted to the City and CMSCWD on Thursday, November 14th.
➢ The plans did not fully encompass the design aspects requested by CMSCWD to construct fully functioning water
treatment basins. CMSCWD has since provided additional comments that are being implemented.
➢ A revised submittal was sent to CMSCWD for review on December 20th, 2024.
➢ CMSCWD sent review comments to the Plowe Engineering on January 10th, 2025.
➢ CMSCWD sent executed watershed permits to the Developer on Wednesday January 15th, 2025.
o Corrective work will take place in the spring due to frost conditions and recent snowfall.
➢ Weather permitting the basin corrective work will begin in June.
➢ Corrective work on the basins is anticipated to be completed by the end of July.
➢ North Pine conducted a site visit in early July and deemed the basins too wet to perform the corrective work. The
Contractor is still hoping to have the corrective work completed by the end of July, weather permitting.
➢ North Pine relayed that the basins are still too wet to perform corrective work but will be working on them as
soon as they are able to. No schedule was submitted.
o CMSCWD is continuing to push for this work to be completed as soon as possible and coordinating
with the developer.
➢ Discussions were had between the Developer and CMSCWD on the remaining basin improvements. It was
decided that a revised plan was required and will be submitted by Plowe Engineering the week of September
15th – 19th for review and implementation.
➢ North Pine plans to begin corrective work on the basins next week and is aiming to be completed by the end of
October.
➢ Corrective work began in mid-November and has had preliminary reviews conducted by CMSCWD for general
compliance.
➢ CMSCWD will confirm the functionality of the recently re-worked basins in the spring.
➢ Outstanding work for CMSCWD to review this spring summer includes:
o Installation of EOF mats and confirmation of vegetation growth from last fall.
o Revegetate and forest the former swale between lots 3 and 4 in the buffer zone.
o Remove and revegetate large stockpile area.
o Remove all debris and silt fencing at closeout.
• Bliss Drainfield System
➢ The final permit has been issued. The assumption is that we’ll end up on Track 2, with required system
improvements due to the nitrate issue. Only thing that needs to take place in the next 6 months (February 28,
2022) is for new flow meters to be installed at the system, something we’ll begin working on. At the one year
mark (September 1, 2022), we’ll need to have a Facility Evaluation Report drafted to summarize the system’s
ability or inability to meet the nitrate limit.
➢ New flow meters were installed by Public Works at the beginning of 2022 and specific flows to the three
drainfield cells is now being monitored. Some additional nitrate testing was also performed in August 2022 to
provide additional data points and to get an idea of how much nutrient removal is currently taking place
through the sand filters.
➢ As of September 1, 2022, the Facility Evaluation Report has been sent to the MPCA. We await their review, but
based on the monitoring well samples taken throughout the last year it appears we’ll be on Track 2, with
improvements to the system needed to deal with the nitrate issue. Assuming this is the case, the next step will
be to complete a full Facility Plan by August of 2023 which evaluates the facility and its performance as a whole
and provides options/recommendations for improvements to be made. This is required by Track 2 but is also the
next step in obtaining PFA funding for the project.
➢ City Council authorized work to complete the facility plan on January 4, 2023. Facility plan to be submitted by
March 3, 2023. Also, Council authorized BMI to complete permit documents for permit modification due to
added treatment for nitrate removal.
➢ Testified at the Capitol on Wednesday, March 1, 2023 requesting funding for the Bliss Wastewater Treatment
Facility.
➢ Facility plan has been submitted for the City of Scandia’s Bliss Wastewater Treatment Facility along with and IUP
request and PPL application to the Minnesota Public Facilities Authority on Friday, March 3, 2023. As of June 22,
the MPCA has issued preliminary approval of this facility plan.
➢ PSIG Funding application was submitted at the end of July (2023). Received follow-up questions from the MPCA
and responses were sent at the end of August (2023).
➢ Response has been received on the environmental review of the project and the DNR has identified the site as
potential nesting land for Blanding’s Turtles. We are working to address the requirements associated with this
in addition to the other revisions.
➢ As of the end of June, the new SDS Permit for the Scandia WW system has been issued. This means that
groundwater monitoring well GW 008 now needs to be sealed within 180 days, as that is part of the permit
requirements.
➢ Per City Staff’s recent funding discussion, BMI has drafted a letter to be formally sent by the City to the MPCA
which explains the situation and all steps that have been taken (and are continuing to be taken) to try and
obtain funding to complete this required project. The letter also requested a modification to the permit schedule
which would extend the timeline to construct from 2025 to 2026 with the assumption that a bonding bill will be
passed which funds PSIG and allows Scandia a realistic path to obtaining this funding. This letter has been
attached to the end of this report for the Council’s review.
➢ The MPCA appears to be open to this process as a viable path forward. Ultimately if this is approved, we will re-
apply for both the CWRF and PSIG programs in 2025 with the goal of being funded for construction in 2026.
➢ BMI re-applied for the 2026 IUP in early June to stay on the PFA’s funding list.
➢ The MN legislature passed a bonding bill in early June, but we are still awaiting specifics prior to knowing how
this will impact our project.
➢ BMI has updated the City’s PSIG Grant Application to get the City of Scandia in line for 2026 funding. We
anticipate that we will know in early November what the City’s position is on the PSIG list. The goal, and hope, is
to be positioned to obtain 80% of the project funding through the PSIG grant program, with the remainder
covered by CWRF low interest loan.
➢ The MN Public Facilities Authority (PFA) has finally released the final 2026 Intended Use Plan (IUP), and it
appears that the Bliss System is set to receive 80% of the project costs in grant (presumably Point Source
Implementation Grant, or PSIG) funding, with the other 20% funded by low interest loans from the Clean Water
Revolving Fund (CWRF). We are moving forward with advertising the project for bids next week and then
opening bids on February 11th.
➢ An addendum was posted on February 6th shifting the bid opening date to February 18th. This allows time for
Contractor’s to submit more accurate pricing information and allows time for the sewer committee to meet
prior to bringing a recommendation of award to Council in March.
➢ The preconstruction meeting for this project was held on Tuesday, April 7th.
➢ MBI plans to begin construction in May to complete the subsurface work, then leave site
until the fall once the building has been completed and ready for delivery.
• 2026 Highway 95 Roundabout Project/CSAH 26 LTL Construction and Realignment
➢ Construct left turn lanes at Hwy 95 at Shamrock Ln. and Hwy 26.
➢ Realign Hwy 26 north to improve turning sight distances.
➢ Construct single lane roundabout at Hwy 243/260th St.
➢ Reconstruct existing shoulders
➢ Build a treatment pond & drainage infrastructure along Hwy 95 at Hwy 26/Pleasant Valley Rd. and Shamrock Ln.
➢ Resurface roadway at the intersection of Hwy 95 and Hwy 243/260th St.
➢ Upgrade drainage at the intersection of Hwy 95 and Hwy 243/260th St.
➢ Project Timeline:
o Spring 2026 through Fall 2026
• Hwy 95 at Hwy 26/Pleasant Valley Rd and Shamrock Ln. Construction
o Spring 2026 through Summer 2026
• Hwy 95 at Hwy 243/260th St. Construction
➢ Project website: https://www.dot.state.mn.us/metro/projects/hwy95franconiatwp/
➢ Traffic impact information is not yet available but should be soon.
o Motorists should expect lane and road closures with detours during construction.
• Highway 95 Future Project Schedule
➢ Street Improvement Projects:
o 2026-2029 Osceola Bridge Project.
• Schedule previously outlined later in this report.
➢ Chip Improvement Projects (typically these projects are placeholders, and often shift based on funding
availability):
o Fiscal Year 2030 – Highway 95 from TH 97 to TH 36 (resurfacing).
o Fiscal Year 2032 – Highway 95 from US 8 to TH 97 (resurfacing).
• Highway 8 Study (Chisago to Taylors Falls)
➢ Project website: https://talk.dot.state.mn.us/hwy-8-chisago-taylorsfalls
o Comments and questions can be submitted on the project website.
➢ Schedule:
o August 2024 through December 2024
• Analyze existing conditions and engage stakeholders.
o January 2025 through August 2025
• Develop and evaluate ideas for improvements with stakeholders and public involvement.
o September 2025 through June 2026
• Finalize study recommendations.
o 2032
• Construction (pavement resurfacing).
• Highway 243 Osceola Bridge
➢ Project website: http://www.dot.state.mn.us/metro/projects/hwy243osceola/index.html
➢ Public Meeting scheduled for May 10, 2023, 5:00pm-7:00pm at the Osceola Village Board Room
➢ Schedule:
o Environmental documentation and preliminary design: 2022 through 2025
o Final design: 2025 through 2026
o Open bids in Spring 2026
o Notice to proceed to be issued in July 2026
o Construction prep work: Fall 2026
o Anticipated construction: 2026 through 2028
• The bridge is anticipated to be closed from fall 2026 through fall 2028.
o Restoration and project completion in 2029.
➢ Project website has been updated with a location plan showing the extents of the work. The project will span the
distance between TH 95 and TH 35.
➢ Traffic Impacts are currently under review, and potential detour plans are being developed.
o See the project website for up-to-date figures.
Denise Workcuff Dmitry Tomasevich
Communications and Engagement Project manager
denise.workcuff@state.mn.us dmitry.tomasevich@state.mn.us
651-775-0025 651-245-4406
➢ The Environmental Assessment Worksheet is now available for public review and comments.
o All comments must be submitted via mail, email, or phone to Dmitry Tomasevich by December
26th.
➢ The Highway 95/Highway 243/260th Street intersection roundabout construction is planned to begin in the
spring of 2026. This will be completed prior to work commencing on the bridge project.
➢ Updated Bridge Closure Information:
o Fall 2026 through Fall 2028
o The Hwy 243 Osceola Bridge over the St. Croix River will be closed. The new bridge
is anticipated to open in Fall 2028.
o Alternate Routes/Detour Figure is included at the end of this report.
• Gateway Trail / County Road 52
➢ Survey update
o Topo survey was completed on November 7th, 2023.
➢ Soil Boring update
o AET submitted the lowest bid at $21,382.00 to perform this work and had the soonest drill rig
availability.
o AET has been authorized to complete soil boring and hand auger boring work on 11/10/2023.
o Soil Borings are scheduled to be completed within 8-10 weeks, with a report coming a few weeks
after completion of field work (Braun was at least a month behind this schedule and came in at
$24,735.00). Hand Auger Borings in off street locations will be completed earlier prior to snowfall.
o AET has been instructed not to begin any work on site until after December 19th. Once approval
has been received, AET will begin hand auger borings (HABs) and then drill rig soil borings (SBs) a
few weeks after.
➢ AET began collecting hand auger borings (HABs) from December 22nd - 26th, and soil borings on December 26th -
29th.
➢ 30% Plans have been compiled to be discussed with City Staff, Washington County, and the DNR at the August
20th monthly meeting.
➢ 60% Plans have been compiled and discussed at our monthly meeting with City Staff, Washington County, and
the DNR on September 17th.
➢ 90% Plans have been completed, and remaining project items are planned to be discussed on December 17th at
our monthly meeting with City Staff, Washington County, and the DNR.
➢ 90% Plan comments have been received from Washington County and are being implemented.
➢ CMSCWD, and wetland impact permit applications will be applied for in the Spring per local rules requiring
contractor submittals within a year of conditional approval.
➢ Kyle Morell and Isiah Bubany met with residents at 15230 and 15240 Oakhill Road on Monday, February 3rd to
discuss design aspects and impacts to each resident’s property.
➢ A trail site walkthrough was requested and will be conducted in the spring/early summer when weather allows
us to further discuss trail alignment location and impacts.
➢ A public information meeting was held on June 11th, from 6:00pm to 8:30pm where project design aspects and
impacts to Scandia residents were discussed at length.
o The City of Scandia, Bolton & Menk, MNDNR, and Washington County all had project
representatives available to answer questions.
➢ Agencies involved with this project will be holding a meeting recap on Tuesday, June 17th at 1:00pm to discuss
which aspects of the project could still be improved upon based on public comments.
➢ A brief project update was provided to Council at the July 2nd Council Workshop. A discussion was had regarding
project design aspects and the associated costs. The outcome of this discussion was to proceed with the project
as scheduled and to request to authorize advertisements for bid in the fall.
➢ The City of Scandia, Bolton and Menk, Washington County, and the MNDNR met multiple times in July to
continue working through finalizing the plans for this project.
➢ Plans and specs are being finalized and will be brought to Council to request authorization to post advertisement
for bids in October.
➢ A request to approve plans and specs and authorize advertisements for bids has been included as a separate
agenda item.
➢ Plans and Specifications were posted soliciting bids at the end of October. Bids will be opened on Wednesday,
November 19th and reviewed prior to conducting an informational meeting with residents and bringing a final
recommendation back to Council in December.
➢ Bids were opened and read publicly on Wednesday November 19th. City Staff, Bolton and Menk, Washington
County, and the MNDNR have reviewed and discussed the bids received to formulate a project presentation and
ultimate recommendation for the project award consideration.
➢ A public meeting was held on December 10th to present the bid information and the plan moving forward; after
which, public comments were received and discussed.
➢ Contracts are being reviewed. Once completed, a pre-construction meeting will be scheduled and tree clearing
will be completed prior to March 31st, 2026.
➢ Notices for construction prep work were distributed on the following dates:
o Private Utility Relocations: February 13th, 2026.
o Construction Limit Staking: February 25th, 2026.
o Tree Clearing Operations: March 10th, 2026.
• Scheduled to be completed by March 31st, 2026.
➢ A preconstruction meeting was conducted on Wednesday, April 15th. A preliminary
schedule is attached to the end of this report.
ID Task Name Duration Start Finish
0 26014 Gateway Trail 94 days Mon 4/27/26 Thu 9/3/26
1 Site Work Trails 60 days Mon 4/27/26 Fri 7/17/26
2 Mobilization 10 days Mon 4/27/26 Fri 5/8/26
3 Locates Private/Public 5 days Mon 5/4/26 Fri 5/8/26
4 Clear and Grub (Tree Top)10 days Mon 5/11/26 Fri 5/22/26
5 Install Temp Creek Crossing 1 day Tue 5/12/26 Tue 5/12/26
6 Construction Entrance 2 days Mon 5/18/26 Tue 5/19/26
7 Initial Deliveries 3 days Mon 5/18/26 Wed 5/20/26
8 Staging Yard Prep 3 days Mon 5/18/26 Wed 5/20/26
9 Removals 4 days Mon 5/18/26 Thu 5/21/26
10 Erosion Control (Central)10 days Mon 5/18/26 Fri 5/29/26
11 Strip Topsoil 5 days Tue 5/19/26 Mon 5/25/26
12 Export Topsoil 3 days Fri 5/22/26 Tue 5/26/26
13 Subgrade- Trails/Parking lot 10 days Mon 5/25/26 Fri 6/5/26
14 Install Fence (Fence)20 days Mon 5/25/26 Fri 6/19/26
15 Cut/Fill 4 days Tue 5/26/26 Fri 5/29/26
16 Install Pipe/Culverts 4 days Thu 5/28/26 Tue 6/2/26
17 One Way Export 1 day Fri 5/29/26 Fri 5/29/26
18 Install 6" Solid DT 1 day Fri 5/29/26 Fri 5/29/26
19 Install Rip Rap 2 days Mon 6/1/26 Tue 6/2/26
20 One Way Sand Import 3 days Mon 6/1/26 Wed 6/3/26
21 Place Topsoil 9 days Wed 6/3/26 Mon 6/15/26
22 Install C5 9 days Mon 6/8/26 Thu 6/18/26
23 Install Kiosk (ATH)2 days Wed 6/17/26 Thu 6/18/26
24 Install Signs (SS)3 days Wed 6/17/26 Fri 6/19/26
25 Install Class 2 Horse Trail 3 days Thu 6/18/26 Mon 6/22/26
26 Tolerance Trails/P.Lot (FC)3 days Mon 6/22/26 Wed 6/24/26
27 Pave Trails (North Valley)2 days Thu 6/25/26 Fri 6/26/26
28 FG Topsoil 5 days Mon 6/29/26 Fri 7/3/26
29 Seed Trails (Central)10 days Mon 7/6/26 Fri 7/17/26
30 Site Work Road 70 days Fri 5/29/26 Thu 9/3/26
31 Install Pre Warning Signs (SS)1 day Fri 5/29/26 Fri 5/29/26
32 Remove Signage 1 day Mon 6/8/26 Mon 6/8/26
33 Re-Locate Mailboxes (Herness)1 day Mon 6/8/26 Mon 6/8/26
34 Install Road Closed Signage (SS)2 days Mon 6/8/26 Tue 6/9/26
35 Install Silt Fence/BMPs (Central)2 days Mon 6/8/26 Tue 6/9/26
36 Sawcut (?)1 day Tue 6/9/26 Tue 6/9/26
37 Reclaim Road (Midstate)2 days Tue 6/9/26 Wed 6/10/26
38 Stockpile Reclaim 3 days Wed 6/10/26 Fri 6/12/26
39 Strip Topsoil 3 days Fri 6/12/26 Tue 6/16/26
40 Cut/Fill 5 days Tue 6/16/26 Mon 6/22/26
41 Sheet Piling Install and Pipe Opening 4 days Thu 6/18/26 Tue 6/23/26
42 Build Road Eastside of box to C5 Grade 5 days Mon 6/22/26 Fri 6/26/26
43 Box Culvert Excavation 2 days Thu 6/25/26 Fri 6/26/26
44 Horse Trail Structural Backfill/Select 2 days Mon 6/29/26 Tue 6/30/26
45 Install Storm 4 days Mon 6/29/26 Thu 7/2/26
46 Pour North Head Wall/Box Footing (JP)10 days Mon 6/29/26 Fri 7/10/26
47 SG Road/Trails 5 days Tue 6/30/26 Mon 7/6/26
48 Build Road Westside of Box 16 days Fri 7/3/26 Fri 7/24/26
49 Two Way Common/Select Sand 1 day Mon 7/6/26 Mon 7/6/26
50 Backfill North Box Footing/Wall 4 days Mon 7/6/26 Thu 7/9/26
51 Reclaim C5 Base for Box Culvert 2 days Tue 7/7/26 Wed 7/8/26
52 One Way Select Sand/Road 3 days Tue 7/7/26 Thu 7/9/26
53 Install 12 P of Box Culvert (AB Crane)1 day Thu 7/9/26 Thu 7/9/26
54 Pour Pipe Sheat Wall Collar (JP)1 day Fri 7/10/26 Fri 7/10/26
55 Install Water Proofing Membrane 3 days Mon 7/13/26 Wed 7/15/26
56 Pour South Headwall/Box Footing (JP)10 days Mon 7/13/26 Fri 7/24/26
57 Sheet Piling Cut and Cap 3 days Wed 7/15/26 Fri 7/17/26
58 Set Last Box Culvert Piece 1 day Fri 7/17/26 Fri 7/17/26
59 One Way Select Sand for Box 3 days Mon 7/20/26 Wed 7/22/26
60 Re-Spread Topsoil 4 days Thu 7/23/26 Tue 7/28/26
61 Install C5 52/Trail 5 days Mon 7/27/26 Fri 7/31/26
62 Install Fence (Fence)10 days Mon 7/27/26 Fri 8/7/26
63 Paint Inside box (Rainbow)4 days Tue 7/28/26 Fri 7/31/26
64 Horse Trail C-2 2 days Thu 7/30/26 Fri 7/31/26
65 Pour Curb/Driveway/Flume (MSC)2 days Thu 7/30/26 Fri 7/31/26
66 Seed Trails To Limits (Central)6 days Fri 7/31/26 Fri 8/7/26
67 Tolerance Road 3 days Mon 8/10/26 Wed 8/12/26
68 Pave Base 52/Trailhead (NV)2 days Thu 8/13/26 Fri 8/14/26
69 Shoulder Road (NV)2 days Mon 8/17/26 Tue 8/18/26
70 Install Signs (SS)3 days Mon 8/17/26 Thu 8/20/26
71 Install Guardrail (H/R)5 days Mon 8/17/26 Fri 8/21/26
72 Install Mailboxes (Herness)1 day Tue 8/18/26 Tue 8/18/26
73 Seed Road Slopes 7 days Tue 8/18/26 Wed 8/26/26
74 Install Pond 6" DT Perf 1 day Thu 8/20/26 Thu 8/20/26
75 Bio Pond Install 2 days Thu 8/20/26 Fri 8/21/26
76 Punchlist 5 days Mon 8/24/26 Fri 8/28/26
77 Pave Wear (NV)2 days Thu 8/27/26 Fri 8/28/26
78 Stripe Road (Century)1 day Mon 8/31/26 Mon 8/31/26
79 Remove Traffic Control (SS)1 day Thu 9/3/26 Thu 9/3/26
26014 Gateway Trail
Mobilization
Locates Private/Public
Clear and Grub (Tree Top)
Install Temp Creek Crossing
Construction Entrance
Initial Deliveries
Staging Yard Prep
Removals
Erosion Control (Central)
Strip Topsoil
Export Topsoil
Subgrade- Trails/Parking lot
Install Fence (Fence)
Cut/Fill
Install Pipe/Culverts
One Way Export
Install 6" Solid DT
Install Rip Rap
One Way Sand Import
Place Topsoil
Install C5
Install Kiosk (ATH)
Install Signs (SS)
Install Class 2 Horse Trail
Tolerance Trails/P.Lot (FC)
Pave Trails (North Valley)
FG Topsoil
Seed Trails (Central)
Install Pre Warning Signs (SS)
Remove Signage
Re-Locate Mailboxes (Herness)
Install Road Closed Signage (SS)
Install Silt Fence/BMPs (Central)
Sawcut (?)
Reclaim Road (Midstate)
Stockpile Reclaim
Strip Topsoil
Cut/Fill
Sheet Piling Install and Pipe Opening
Build Road Eastside of box to C5 Grade
Box Culvert Excavation
Horse Trail Structural Backfill/Select
Install Storm
Pour North Head Wall/Box Footing (JP)
SG Road/Trails
Build Road Westside of Box
Two Way Common/Select Sand
Backfill North Box Footing/Wall
Reclaim C5 Base for Box Culvert
One Way Select Sand/Road
Install 12 P of Box Culvert (AB Crane)
Pour Pipe Sheat Wall Collar (JP)
Install Water Proofing Membrane
Pour South Headwall/Box Footing (JP)
Sheet Piling Cut and Cap
Set Last Box Culvert Piece
One Way Select Sand for Box
Re-Spread Topsoil
Install C5 52/Trail
Install Fence (Fence)
Paint Inside box (Rainbow)
Horse Trail C-2
Pour Curb/Driveway/Flume (MSC)
Seed Trails To Limits (Central)
Tolerance Road
Pave Base 52/Trailhead (NV)
Shoulder Road (NV)
Install Signs (SS)
Install Guardrail (H/R)
Install Mailboxes (Herness)
Seed Road Slopes
Install Pond 6" DT Perf
Bio Pond Install
Punchlist
Pave Wear (NV)
Stripe Road (Century)
Remove Traffic Control (SS)
S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T WApr 26, '26 May 3, '26 May 10, '26 May 17, '26 May 24, '26 May 31, '26 Jun 7, '26 Jun 14, '26 Jun 21, '26 Jun 28, '26 Jul 5, '26 Jul 12, '26 Jul 19, '26 Jul 26, '26 Aug 2, '26 Aug 9, '26 Aug 16, '26 Aug 23, '26 Aug 30, '26 Sep 6, '26 Sep 13, '26May 2026 June 2026 July 2026 August 2026 September 2026