Engineering Updates 4/18/2017
• 2017 Seal Coat Project
➢ Will be on the City Council agenda as a separate business item to award the
project. Work would only begin after the annual patching project is completed.
• 2017 Crack Filling Project
➢ Work is anticipated to occur in late May to early June.
• Soil Boring Quotes
➢ Will be discussed as a separate business item during the City Council meeting,
see location map below for reference of soil borings to be completed.
• Comprehensive Plan Update
➢ Project website (https://www.bolton-menk.com/clients/scandia/index.html)
➢ Prepared materials for the next Steering Committee, scheduled for April 201h at
6:30 PM. The Committee will discuss the results of the SWOT exercise, and will
draft questions for the community comprehensive plan survey.
➢ We have received 60 responses on the current short survey on the website.
• Miscellaneous Items
➢ Staff met with City Staff on March 22nd to complete drawdown tests on all the lift
stations for the Bliss #1-4, Anderson/Erickson, and Uptown System to determine
pump capacity, condition, and identify any operating issues.
➢ Completed a road tour with Public Works on April 10tH
➢ Will be presenting to the Capital Improvement Plan Committee on May 4th
Soil Boring Location Map