COAX Email1
Kyle Morell
From:Tim Ramler <Tim.Ramler@midco.com>
Sent:Thursday, June 18, 2026 10:45 AM
To:Kyle Morell; Hayden Lamoureux
Cc:Andrew Curley; Elly Burroughs
Subject:Re: [EXTERNAL] - Scandia Border 2 Border Project Update
Hi Kyle,
I spoke with our Regional Construction Manager and Midco is working on upgrading our coax cable
network across our footprint as needed. Current plan is to have all upgrade work completed by end of
2028. The upgrade work will not change the existing coax line to the home but will improve on speeds and
congestion.
Thanks,
Tim
To help protect your privacy, Microsoft Office prevented automatic download of this picture from the Internet.
Tim Ramler
Central Construction Project Manager
Office: 6125032091
Tim.Ramler@midco.com
Midco.com
Let's go beyond.
From: Kyle Morell <k.morell@ci.scandia.mn.us>
Sent: Thursday, June 18, 2026 8:57 AM
To: Hayden Lamoureux <Hayden.Lamoureux@midco.com>
Cc: Tim Ramler <Tim.Ramler@midco.com>; Andrew Curley <Andrew.Curley@Midco.com>; Elly Burroughs
<Elly.Burroughs@midco.com>
Subject: RE: [EXTERNAL] - Scandia Border 2 Border Project Update
Hayden,
Thank you for sending this over.
I have another question. The Committee has asked about potential updates/upgrades to existing coax lines. Is this
something that is on Midco’s radar?
Kyle H. Morell
City Administrator
City of Scandia
14727 209th Street North
Scandia, MN 55073
Phone: 651.433.2274 Fax: 651-433-5112
Cell: 651.245.2654
Web: www.cityofscandia.com
Email: k.morell@ci.scandia.mn.us
2
From: Hayden Lamoureux <Hayden.Lamoureux@midco.com>
Sent: Tuesday, June 16, 2026 4:49 PM
To: Kyle Morell <k.morell@ci.scandia.mn.us>
Cc: Tim Ramler <Tim.Ramler@midco.com>
Subject: RE: [EXTERNAL] - Scandia Border 2 Border Project Update
Here’s an update for the committee meeting,
The project continues to move forward as we are currently working through several private easements
that are still in process. In addition, we are awaiting a response from the Canadian National Railroad
regarding two crossings that are required before we can move forward with launching. As we are waiting
for the responses from the railroad as well as the private easements, crews are continuing to make
progress through the remaining areas of the project. we are still planning to launch service to new
residents later this summer. Midco is also looks forward to once again sponsoring Scandia Community
Fun Day on August 19th. This year's event will provide a great opportunity to celebrate the progress of
this project and the work that has gone into connecting Scandia.
For additional information and ongoing updates, residents can visit https://midco.com/hellopage.
To help protect your priv acy, Microsoft Office prevented automatic download of this picture from the Internet.
Hayden Lamoureux
Central Construction Coordinator I
Office: 7012135198
Hayden.Lamoureux@midco.com
Midco.com
Let's go beyond.
From: Kyle Morell <k.morell@ci.scandia.mn.us>
Sent: Tuesday, June 16, 2026 8:27 AM
To: Hayden Lamoureux <Hayden.Lamoureux@midco.com>
Subject: [EXTERNAL] - Scandia Border 2 Border Project Update
CAUTION: This email originated from outside of MIDCO.
Do not click links or open attachments unless you recognize the sender and know the content is safe.
Hayden,
The City of Scandia’s Internet Action Committee is meeting on Thursday. They would appreciate an update on the
project's progress in town. Anything you can provide would be appreciated.
Kyle H. Morell
3
City Administrator
City of Scandia
14727 209th Street North
Scandia, MN 55073
Phone: 651.433.2274 Fax: 651-433-5112
Cell: 651.245.2654
Web: www.cityofscandia.com