06.m 2026 Crack Fill and Seal Coat Project - Contractor's Request for Payment No 1
14727 209 th St. N., Scandia, Minnesota 55073
Phone (651) 433 -2274 Fax (651) 433 -5112 https://www.cityofscandia.com
July 21, 2026
Honorable Mayor and City Council
City of Scandia
14727 209th Street N.
Scandia, MN 55073-8503
Re: Contractor’s Request for Payment No. 1
2026 Crack Fill and Seal Coat Project
Dear Mayor and Council:
Enclosed please find Contractor’s Request for Payment No. 1, for the 2026 Crack Fill and Seal
Coat Project. We recommend the council approve the Contractor’s Request for Payment No. 1
and pay $19,942.86 to Fahrner Asphalt Sealers, LLC. This amount includes work required to
mobilize to site, place traffic control, route and seal cracks on the project. This request includes
withholding 5% retainage.
Please call me at (651) 308-1491 if there are any questions or concerns regarding this
Contractor’s Payment request.
Sincerely,
Isiah C. Bubany, P.E.
Project Engineer
Enclosures: Contractor’s Request for Payment No. 1
Contractor's Application for Payment
Owner's Project No.:
Engineer's Project No.:
Agency's Project No.:
1 From 06/01/26 to 06/30/26
A C D E F F1 F2 G H I J K L
Item Quantity Units
Unit Price
($)
Value of Bid Item
(C X E)
($)
Quantity Previous
Estimate
Value Previous
Estimate
Estimated
Quantity
Incorporated in
the Work
Value of Work
Completed to Date
(E X G)
($)
1 1.00 LS 7,500.00 7,500.00 - 0.50 3,750.00 3,750.00 50% 3,750.00
2 1.00 LS 1,000.00 1,000.00 - 0.50 500.00 500.00 50% 500.00
3 8,290.00 GAL 2.82 23,377.80 - - - - 23,377.80
4 250.00 TN 58.16 14,540.00 - - - - 14,540.00
5 2,630.00 LBS 3.44 9,047.20 - 4,867.00 16,742.48 16,742.48 185% (7,695.28)
6 10,360.00 LF 0.39 4,040.40 - - - - 4,040.40
59,505.40 - 20,992.48 - 20,992.48 38,512.92
7 1,380.00 GAL 2.82 3,891.60 - - - - 3,891.60
8 50.00 TN 58.16 2,908.00 - - - - 2,908.00
9 430.00 LF 2.50 1,075.00 - - - - 1,075.00
7,874.60 - - - - 7,874.60
67,380.00$ -$ 20,992.48$ -$ 20,992.48$ 31% 46,387.52$ BASE QUOTE + ALTERNATE TOTAL
BITUMINOUS MATERIAL FOR SEAL COAT
SEAL COAT AGGREGATE, FA-2 MODIFIED
ALTERNATE 1: PUBLIC WORKS PARKING LOT TOTAL
PAVEMENT MARKING LINES - PAINT (YELLOW)
BITUMINOUS MATERIAL FOR SEAL COAT
BASE QUOTE TOTAL
SEAL COAT AGGREGATE, FA-2 MODIFIED
PAVEMENT MARKING LINES - PAINT (WHITE)
ROUTE AND SEAL CRACKS
Contract:
Work Completed
Materials Currently
Stored (not in G)
($)
Work
Completed
and Materials
Stored to Date
(H + I)
($)
Contract Information
Bid Item
No.
Application Date:Application Period:Application No.:
Previous Estimate
07/21/26
B
BASE QUOTE
% of
Value of
Item
(J / F)
(%)
Balance to Finish
(F - J)
($)
MOBILIZATION
TRAFFIC CONTROL
Description
Progress Estimate - Unit Price Work
City of Scandia
Bolton & Menk, Inc.
Fahrner Asphalt Sealers, LLC
2026 Crack Fill and Seal Coat Project
Owner:
26X.142964Engineer:
Contractor:
Project:
Unit Price
EJCDC C-620 Contractor's Application for Payment