Engineering Updates 5/16/2017
• 2017 Seal Coat Project
➢ Process of preparing contracts, work anticipate to begin end of July.
• 2017 Crack Filling Project
➢ Work is anticipated to start the week of May 15tH
• Soil Boring Quote Work
➢ Fieldwork has been completed other than some work needs to be redone on
filling a few of the soil boring holes. Anticipate having the report by end of May
2017.
• Comprehensive Plan Update
➢ Project website (https://www.bolton-menk.com/clients/scandia/index.html)
➢ Held Steering Committee meeting on April 20th to discuss the community
comprehensive plan survey.
➢ Revised survey sent to committee members on April 26' with responses due by
May 4tH
➢ Looking at formatting survey for mailing and return responses.
➢ Working on scheduling Youth, Senior and Business/Agricultural focus groups in
May.
➢ We have received 62 responses on the current short survey on the website.
• Washington County
➢ Country Road 52/Oakhill Road between TH 95 and Hwy 97 is still planned for
2018 construction. The County is also planning on resurfacing CSAH 3 from CSAH
4 to the Wash ington/Chisago County line.
• MnDOT
➢ 1-35 — Six miles of 1-35 from just south of the 1-35 split to a half mile north of Hwy
8 at the Chisago/Washington county line will be resurfaced. Construction
schedule is anticipated July 2017 through 2019. The work will also include
replacing three bridges located at:
• Hwy over 1-35, Hwy 97 over 1-35,1-35 W over 1-35E
• http://www.dot.state.mn.us/metro/projects/351inolakes/index.html
• Miscellaneous Items
➢ Discussed pedestrian funding opportunities with Susan Rodsjo, Mayor Christine
Maefsky, and City Administrator on May 2nd
➢
tH
Presenting to the Capital Improvement Plan Committee on May 4