8.d Engineering Updates City of Scandia
Engineering Updates 12/19/2017
Engineering
• 2017 Seal Coat Project
Work has been approved and IC-134’s and lien waivers have been obtained. On
the agenda as a separate business item will include Contractor’s Request for
Payment No. 2 & Final.
• 2017 Spray Patching Project
Work has been completed and approved and IC-134’s and lien waivers have
been obtained. On the agenda as a separate business item will include
Contractor’s Request for Payment No. 2 & Final.
• Comprehensive Plan Update
Project website (https://www.bolton-menk.com/clients/scandia/index.html)
We are currently drafting the text of the Comprehensive Plan and will begin
distributing chapters for review in December.
City staff will start bringing the chapters to the Planning Commission in January.
• Miscellaneous
2018 Street Project
• Field survey work has been completed and approximately 70% of the
existing culverts have been inspected. Upon completing all inspections a
complete inventory/conditions assessment will be completed to identify
which culverts need to be replaced.
Comments on the Washington County Draft five-year Capital Improvement Plan
(CIP) were submitted on November 22nd.
We will be participating in Vinterfest and the Snow Sculpture event again on
January 27, 2018, however instead of medals we will be providing the self-
standing acrylics to the participants as shown below!
Merry Christmas & Happy New Year