ENGINEERING UPDA TE
October 16, 2092
The purpose of this update is to provide information on current projects and engineering in Scandia.
2012 Seal Coat and Bituminous Patchinq Project
• Final Contractor's Request for Payment for is ready for approval. Final costs are
approximately 5.5% less than the original bid amount.
Pavement Manaqement Plan Update
• We have been working with Tim Kieffer on priority modifications to the Pavement
Management Plan.
Anderson/Erickson Sewaqe Treatment System
• We have been meeting with the Wastewater Advisory Committee regarding issues with this
system. A draft policy for future connections will be presented at the November 1, 2012
Wastewater Advisory Committee meeting.
• Working with Tim Kieffer and EcoCheck on list of repairs that need to be completed in the
near future.
• The fall 2012 monitoring well sampling will be completed this month.
Uptown Wastewater System Improvements
• Discussed coordination and easement issues with Tim Kieffer. Construction is scheduled to
be substantially complete this month.
CSAH 3/Olinda Trail Curb and Sidewalk Replacement Proiect
• Work on this Washington County project continues. They will install a pedestrian ramp on the
SE corner of 209th and Olinda. Work should be substantially complete this month.
Tii Gavo
• The Washington County Conservation District has issued a certificate of compliance. The
CMSCWD has indicated that they require some additional information from the developer
regarding the drainage features.
• City staff reviewed the site in October. Most of the items on the Final Inspection Notice have
been addressed by the Developer. The remaining items can be completed in the spring of
2013. At that time, the City can complete a comprehensive review of the project (including
landscaping) and consider a reduction in the project sureties.
Bone Lake Fish Barrier (CLFLWD Proiect)
. The project is substantially completed. There is some minor clean up, seeding and punch list
work left to be completed. Tim is working with the watershed district regarding concerns with
the bituminous patch on 238�'.
Goose Lake Ravine Stabilization Proiect (CMSCWD Proiect)
• The preconstruction conference was held on 10/12. Construction (Scandia Trucking and
Excavating) should begin this week, Tim will watch this project along with CMSCWD staff.
City of Scandia—Engineering Update