8.f Public Works Report - February 2018March 20th, 2018
Public Works Staff Report – February 2018
Roads and Right – of – way
ROW Brush clearing – 2018 road improvement areas: hand work –
completed – working on other areas of concern
ROW – additional Brushing with tractor – 220th, Maxwill, Mayberry,
Lakamaga
Downtown lighting dead short identified – East side lights working
Snow – 3 – full scale plows 18” total snow plowed – 7 times out
scraping / de-icing
Gravel roads: Adding grit for traction to gravel roads – 8 times – 197th
every other day.
197th steamed out culver on from it freezing up – springs
Sewer – Water:
February ‘18 - sewer samples were taken at Bliss
201 – January Monthly DMR completed
Uptown - Monthly water meter readings completed
201 – one residential pump replaced, one residential control cabinet
replaced, one check valve replaced, three pumping’s of residential
systems for repairs
201 – Bliss – Lift station #1 – coming 3-13-18
3 Gopher One call requests
Parks:
Monthly safety checks done on playgrounds
Rink maintenance – Zamboni each day
- New netting to cover NE corner ready for next year
- Pushed back Zamboni dump pile
Lilleskogen Park –STS – continued buckthorn removal – there are 2
more days in March reserved for Scandia
Sidewalks / rink: Snow blown 4 times
Other:
LED light unloading for City Hall light replacements
Monthly building safety checks completed
AED – Community Ctr. - Updated pads and battery