8.d) 2014-5-20 Engineering Updatest SCANDIA Engineering City of Scandia Engineering Updates 5/20/2014 • 2014 Route & Seal Project has been completed. Area of work included the City Hall Parking Lot and Meadowridge Lane/Circle/Trail roadways within Tii Gavo. Work completed has been reviewed by Engineer and Public Works and found to be completed per project requirements. Higher amount of quantity was used than anticipated because of the size and depth of cracks within the City Hall Parking lot that required a double fill. • 2014 Seal Coat project will start work after the patching work has been completed. • Coordination with Public Works has been ongoing with planned future improvements within Lilleskogen Park. • Chloride Application quotes have been obtained and will be discussed at the May 20tn City Council meeting. • Geotechnical Services to complete soil borings and a report have been obtained. Quotes will also be discussed at the May 20t" City Council meeting.