Loading...
8.d Engineering Report City of Scandia Engineering Updates 6/19/2018 Engineering italics = old information • Comprehensive Plan Update Project website updated to include status and current draft (https://www.bolton- menk.com/clients/scandia/index.html) Presented plan at the City Council meeting on 5/15/18. The Council approved the draft plan. Plan was distributed to adjacent communities for review 5/31/18. Comments are due by 12/1/18. Plan was submitted to Met Council for preliminary review on 6/14/18. Preliminary review is an informal review by the Met Council and generally takes 30-60 days. This will give us a preview of any comments or concerns they may have prior to formal review. • 2018 Street Project Weekly/current construction updates are posted on the City’s website, link is: “2018 Street Improvements Projects” Substantial amount of work has been completed on 230th Street N, Kirk Ave N, Melanie Trail N. Culvert work has been completed on 228th Street N, and Mallard Ave N. Contractor currently focusing on Oxboro Ave N and Old Marine Road N area to ensure the first lift of pavement is placed prior to the Fat Cat Triathlon. Contractor’s Request for Payment No. 1 on agenda as separate business item. • Washington County Construction Projects County Road 52 (Oakhill Road) • Oakhill Road North (County Road 52) from Hwy 95 to Hwy 97 • Contractor is trying to have all the bituminous paving completed by the 4th of July with the final striping to follow. County Highway 3 (Olinda Trail) • Olinda Trail (County Highway 3) from 170th Street (CSAH 4) to Old Marine Trail • Schedule, August – September 2018 • Project has not had the Bid opening. • Miscellaneous Spray Patching & Crack Filling • Both projects are anticipated to start the week of June 18th. Layton Ave N/ Bliss Addition (Holiday Beach Plat) • In process of preparing a quote package to complete some ditch work and culvert cleaning. Intent would to bring to the July 17th City Council meeting for potential award.