8.d Engineering UpdatesSCANDIA
City of Scandia
QBOLTON
& MENK
Engineering Updates 7/11/2018
Engineering italics = old information
• Comprehensive Plan Update
➢ Project website updated to include status and current draft (https://www.bolton-
menk.com/clients/scandia/index.html)
➢ Plan was distributed to adjacent communities for review 5/31/18. Comments are
trickling in (no substantive comments yet). All comments due by 12/1/18.
➢ Plan was submitted to Met Council for preliminary review on 6/14/18. Preliminary
review is an informal review by the Met Council and generally takes 30-60 days. We
have not received any response at this time.
• 2018 Street Project
➢ Weekly/current construction updates are posted on the City's website, link is:
"2018 Street Improvements Projects"
➢ Contractor to begin roadway construction the week of July 16th on 228th Street,
Mallard Ave, Meadowbrook Ave, and Oakhill Road. 54" culvert replacement/detour
on Oakhill Road scheduled this week as well.
➢ Contractor's Request for Payment No. 2 on agenda as separate business item.
➢ Change Order No. 1 has been prepared to add the additional streets to the existing
project as shown on a figure attached to the agenda item.
Washington County Construction Projects
➢ County Road 52 (Oakhill Road)
Oakhill Road North (County Road 52) from Hwy 95 to Hwy 97
• Contractor has completed wear course and placed temporary stripes. Final
striping will occur after July 20tH
➢ County Highway 3 (Olinda Trail)
• Washington County has decided not to proceed with CSAH 3 in 2018, future
schedule is going to be reviewed at a later time.
Miscellaneous
➢ Spray Patching & Crack Filling
• Spray patching project is anticipated to finish the week of July Stn, upon
completion they will sweep the roadway to ensure it's clean & safe for the
triathlon.
• Crack filling project has been finished and on agenda as a separate item is
Contractor's Request for Payment No. 1 and final.
➢ Layton Ave N/ Bliss Addition (Holiday Beach Plat)
• Three quotes have been received, as a separate agenda item potential
award for the ditching/culvert cleaning will be presented.
➢ Small Cities Assistance Account
0 2018 Allocation for Scandia - $39,716