8.c) City Engineer i Meeting Date: 10/20/09 Agenda Item: �'/ C , City Council Agenda Report City of Scandia 14727 209th St. North Scandia, MN 55073 (651) 433-2274 Action Requested: Receive a report from the City Engineer on the 2009 Crack Seal Project, and approve Pay Request# 1 and Final to Astech (Asphalt Surface Technologies Corporation) in the amount of$23,885.50. Deadline/ Timeline: N/A Background: • At the July 21 meeting, the Council awarded a contract for the crack sealing project to Astech in the amount of$86,800. The original conshuction cost estimate was $164,000. • The quantity of crack sealing material used on the specified streets was significantly less than expected. Astech rejected a change order to add additional streets. A"phase 2"crack sealing project was awarded to Asphalt Associates in September. • The Engineer has reviewed the request for payment and found it to be in order. Recommendation: I recommend that receive a report from the City Engineer on the status of the crack sealing project, and approve the pay request to Astech. Attachments/ • Pay Request Materials provided: Contact(s): Paul Hornby, PE Prepared by: Anne Hurlburt, Administrator (2009 crack seal project final payment astech) Page 1 of 1 10/15/09 i 2335 Highway 36 W St.Paul,MN 55113 Tel 651-636-4600 Fax 651-636-1311 www.bonestroo.com October 15, zoo9 �Bonestroo Ms. Anne Hurlburt City Administrator City of Scandia 14727 209`h Street N Scandia, MN 55073 Re: Contractor's Request for Payment #1/Final 2009 Crack Seal Project—Phase 1 Our File No: 000568-09139-0 Dear Ms. Hurlburt: Enclosed please find Contractor's Request for Payment #1/FINAL from Asphalt Surface Technologies Corporation (ASTECH) for the services they provided on Phase 1 of the 2009 Crack Seal Project. The project included crack sealing of various streets throughout the City. it would be appropriate to approve payment for the requested amount of$23,885.50 to Asphalt Surface Technologies Corporation for the work pertormed. This payment includes release of the final retainage for the project. All work under Phase 1 of this project was completed in August 2009. At this time, it would be appropriate for the City Council to formally accept Phase 1 of the project as oomplete. The final construction cost for Phase 1 of the project was $23,885.50. Please feel free to contact ]eremy Hauser or me at if there are any questions or concerns regarding this payment request. Sincerely, BONESTR00 —�------- � � Paul Hornby, P.E. City Engineer st.Paul St.Cloud Rahester Milwaukee Chicago � � � Owner. Ci of Scandia, 14727 209th St N , P 0 Box 128, Scandia, MN 55073 Date: October 15, 1009 For Period: 1011I2009 to 10/1512009 Re uest No: 1 AND FINAI Bonestroo Contractor Astech Surface Technolo ies, P 0 Box 1025, St Cloud, MN 56302 CONTRACTOR'S REQUEST FOR PAYMENT 2009 CRACK SEAL PROIECT BONESTR00 FILE NO 000568-09139-0 SUMMARY 1 Original Contract Amount 3 86,800.00 2 Change Order -Addition $ 0.00 3 Change Order- Deduction $ 0.00 4 Revised Contrad Amount $ 86,800.00 5 Value Completed to Date $ 23,885.50 6 Material on Hand 3 0.00 7 Amount Earned $ 23,885.50 8 Less Retainage 0% $ 0.00 9 Subtotal $ 23,885.50 10 Less Amount Paid Previously 3 0.00 11 Liquidated damages- $ 0.00 12 AMOUNT DUE THIS REQUEST FOR PAYMENT N0. 1 AND FINAL $ 23,885.50 Recommended for Approval by: BONESTR00 Approved by Contractor: Approved by Owner: ASTECH SURFACE TECHNOLOGIES CITY OF SCANDIA Specified Contract Completion Date Date: 56809139R E O 1 F I NAL.xls