Engineering Updates 9/18/2018
Engineering italics = old information
• Comprehensive Plan Update
➢ Project website updated to include status and current draft (https://www.bolton-
menk.com/clients/scandia/index.html)
➢ Plan was distributed to adjacent communities for review 5/31/18. Comments are
trickling in (no substantive comments yet). All comments due by 12/1/18.
➢ Plan was submitted to Met Council for preliminary review on 6/14/18. Preliminary
review is an informal review by the Met Council. We received comments on July 17,
2018.
➢ We are looking at necessary revisions as a result of Met Council comments, and
revisions required to add new land use category of Rural Mixed Use.
• 2018 Street Proiect
➢ Weekly/current construction updates are posted on the City's website, link is:
"2018 Street Improvements Projects"
➢ Contractor has continued working on shouldering and now have completed several
areas. Old Marine Road, Oxboro and Orwell are next areas to be shouldered.
➢ Remaining areas to be paved include 199th Street/Parkview which is scheduled for
the week of September 17tH
➢ Guardrail work is scheduled to begin the week of September 17th as well, starting
on areas north of Hwy 97.
➢ Contractor's Request for Payment No. 4 on agenda as separate business item.
• Miscellaneous
➢ Spray Patching
• All work has been completed and approved. Separate agenda items will
include Contractor's Request for Payment No. 2 and Final.
➢ Layton Ave N/ Bliss Addition (Holiday Beach Plat) — Ditching/Culvert Cleaning
• Peterson Excavating, Inc. has completed the work. Final touch up work to
follow along with waiting for final establishment of restoration.
➢ Gateway State Trail Extension
• Met with the DNR/City Staff on 9/6 to discuss scope of work design work
from Oakhill (CR 52) underpass crossing up towards to City owned property
(14800 Oakhill Road).