Engineering Updates 4/16/2019
Engineering italics = old information
Comprehensive Plan Update
➢ Project website updated to include status and current draft (https://www.bolton-
menk.com/clients/scandia/index.html)
➢ We received additional comments from the Met Council in March, and followed up
with a conference call to discuss the additional comments. Additional information
was submitted to Met Council staff on April 9th
➢ Once the plan has been determined to be complete, it will proceed through the Met
Council committee process. The status of the plan can be tracked on the Scandia
Community Page on the Met Council website at
https://Iphonline.metc.state.mn.us/CommPage?ctu=2396548&applicant=Scandia
2018 Street Project
➢ Weekly/current construction updates are posted on the City's website, link is: '2018 Street
Improvements Projects"
➢ Record plans have been completed and currently being reviewed by Public Works.
➢ Project walk-through will be conducted in the spring, any outstanding items will be addressed and
completely prior to project closeout.
• Miscellaneous
➢ Gateway State Trail Extension
• Specific Property owner meetings have been held on 10/31/18 and 11/14/18, ongoing
coordination has continued to occur.
• All wetland & preliminary field survey work has been completed including completion of the
wetland delineation report. TEP meeting was held on 11/30/18.
• Attended a Technical Design meeting with the DNR & City Staff on 12/19/18 to discuss
project constraints along CR 52, thus a meeting with the County has been scheduled for
1/11/2019 to presents options.
• Public Open House held on March 19, 2019 was well attended and a lot of
support for the project was shown. Inquires of concerns were addressed by
the DNR along with a lot of long-term planning questions were received.
• DNR, Washington County, Design Staff met on April 9, 2019 to discuss what
Washington County will require where the proposed trail runs adjacent to
County Road 52. These requirements will be a significant amount of work
scope change so we need work through with the DNR on who will be
completing what tasks prior to proceeding.
➢ Bliss Addition Stormwater Planning
• Includes 190th Street N, 189th Street N, Layton Ave and Larksupur Ave N
circle area.
• Public Outreach meeting being held at City Hall with the adjacent property
owners prior to the City Council meeting, on April 16, 2019, from 5:30pm —
6:30pm.
➢ Lilleskogen Park — Expedited Conservation Project Grant
• Grant application was due on March 18, 2019, application was submitted a
couple days prior, notice of grant award if successful is anticipated around
April 26, 2019. Grant is a Minnesota Department of Natural Resources
(MnDNR) Expedited Conservation Partners (ECP) grant. This program is part
of the MnDNR's Conservation Partners Legacy (CPL) program. The grant
application title is "Lilleskogen Park Restoration".
➢ Bliss Drainfield System
• Been working on gathering information and will start to review results so the Nitrogen
Mitigation Plan can be prepared for MPCA approval within on year of permit issuance.
• Waiting to hear results of discussion between the City and MPCA about the
possibility of drilling a new monitoring well to replace GW004. The nitrogen
memo and application renewal of the permit is due 180 days prior to the
permit expiration which is September 2019, existing permit expiration date
is in February 2020.
➢ Bliss Control Panels
• Quote package is in the process of being prepared, however waiting to
obtain some field information prior to finishing. Plan to send out to
Contractors in May. Also looking into the costs to complete a radio SCADA
telemetry study, once costs are estimated separate discussion will be held
with the City.
➢ Community Water Study (Fire Station Area)
• Just recently received the go-ahead, future updates will include more
details.
➢ Capital Improvement Plan
Completed a road tour with Public Works on March 29, 2019 to review
roadways for consideration for the planned 2020 Street Improvement
Project. Process of preparing cost estimates of road segment candidates for
future discussions at Capital Improvement Committee Meetings.