9.c Engineering UpdatesI
SCANDIA
QBOLTON
& MENK
City of Scandia
Engineering Updates 7/21/2020
Engineering italics = old information
2020 Street Improvement Project
➢ Field review with Public Works has been completed on January 14th.
➢ Project is currently out for bid, bid open date February 20, 2020 at 10:OOam.
➢ City Council awarded the project to Valley Paving, Inc. at the March 17, 2020 City Council Meeting.
➢ Contracts have been executed, preconstruction meeting is scheduled for Monday, April 20, 2020 at
10:30am. Contractor plans on starting week of April 27, 2020
➢ All work has been completed and approved, as a separate business item, Contractor's
Request for Payment No. 3 and Final will be presented.
Washington County's first Bicycle and Pedestrian Plan
➢ Our fist TAC meeting was held on Wednesday, August 14th, 2019.
➢ Second TAC Meeting was held on Monday, December 16, 2019. To recap, the meeting included a
project update and review of the existing conditions report. The project consultant also presented
preliminary ideas on how the future county bicycle and pedestrian network maybe laid out. Moving
forward, we plan to hold two more TAC meetings (February and April 2020). We have also decided to
schedule our next round of pop-up events for March/April and open houses in May/June. In the
meantime, we will continue to provide project updates online and online engagement activities. We
plan to launch an online survey after the holidays.
➢ TAC Meeting #3 was held virtually on March 25, 2020. The planning consultant used this time to
present draft materials, which included a revised Future Network map and a methodology for
prioritizing future projects.
➢ Current online survey link has been shared with City Councils and Communities and is posted on the
City's website. The purpose of this survey is to gain even further insight into specific preferences and
barriers that residents face. This information will assist in fine-tuning a network plan and future
recommendations, as well as help to prioritize future opportunities.
➢ County is planning for some public engagement (online) by end of month or early August to
get reactions on the draft Plan and seek recommendations.
➢ Project Manager, Emily Jorgensen
• emily.iorgensen@co.washington.mn.us
• 651-430-4338
• https://www.co.washington.mn.us/bikepedplan
Public Works/Fire Hall Parking Lot Improvements
➢ Project was awarded to Bluhm Construction at April 21, 2020 City Council Meeting.
➢ Anticipated construction currently is looking to start in July, project contract does have a
specified completion date of August 291H
➢ Contractor will begin construction on July 15th with mudjacking concrete slabs.
➢ Contractor will begin Concrete curb & gutter and milling the week of July 201H
➢ Completion of project anticipated before July 31, 2020.
Bliss Drainfield System
➢ Both the 2020 permit application for this system and the 'final report" for nitrogen mitigation have
been completed and submitted to the MPCA. The memo which serves as a final report doesn't
present final solutions for the nitrogen issue, but instead outlines the issues that have been found
and solved in this treatment system, as well as some additional testing that will now be
recommended to get a handle on the nitrogen, BOD, and TSS entering and leaving the facility. The
hope is to gain us a little more time from the MPCA before they mandate action. We'll use this time
to perform the aforementioned testing and evaluate options for removing nitrogen at Bliss.
➢ To date we still have not heard anything from the MPCA regarding the permit and this is very typical.
This means the City's existing permit is still in effect until the new permit is issued.
Sump Pump Inspection Program
➢ 3 homes/cabin remain to be inspected. City moving forward with issuing a citation to one property, a
final letter to the second property requesting an inspection, and third property doesn't have their CO
issued yet and will be inspected during routine building inspections.
Bliss Addition Stormwater Planning
➢ Public Outreach meeting being held at City Hall with the adjacent property owners prior to the City
Council meeting, on April 16, 2019, from 5:30pm — 6:30pm.
➢ Met with watershed district on 8/2 to discuss preliminary options for expanding regional water
storage, restoring infiltration capacity and improve water quality. The watershed made some great
recommendations for managing overall project costs and those options are currently being explored.
➢ Second public meeting occurred on August 20th. Preliminary storm water management practices
were presented to the residents and were well received. Some new recommendations were also
presented and considered in the plan revisions.
➢ Final Draft will be presented to the City Council at the November 19, 2019 meeting.
➢ Meeting with City Staff and Watershed District was held on January 16, 2020 to discuss prioritization
and implementation schedule for the items presented in the final storm water study. Separate costs
estimates have been put together based on the prioritization which will be used for future funding
submittals.
➢ Recent engagement with the Carnelian Marine St. Croix Watershed District resulted in the
two bullet points below:
Cost responsibility -Who would take on what costs and how? Ideally the District
would like to participate with a Clean Water Fund Grant.
Timeline - The District is working to complete the Subwatershed analysis for Big
Marine Lake. It will be complete by June 2021. Clean Water Fund Grants are
awarded based on how the score. Without a completed Subwatershed analysis for
the entire lake and application would score low. We planned to apply for a CWF
grant in the fall of 2021 (after the completion of the analysis). If the City would like
to dedicate funding and move up the timeline, they could request the CMSCWD
Board of Managers consider funding a phase of the project without a CWF grant. I
do know that next year's budget is tight with the state required 10 -year
management plan update.
CLFLWD Comprehensive Watershed Management Plan
➢ Watershed District staff reviewed the following topics with the City staff though a Zoom Meeting on
May 12, 2020. Some of the topics included; Lakes (pollutants, recreational use, shoreline), Aquatic
invasive species, Stormwater management (Low Impact Development, rules), Floodplain (flood
resiliency), Resiliency planning (climate adaptation, development demands), Groundwater (quantity
and quality)
➢ Below is a brief summary of immediate next steps and major checkpoints:
• May 2020
• Continue issues workshops, engaging TAC members in small groups
• Coordinate at the staff level with cities and townships
• Review EOR scope of work for next phase of plan update process
• Workload Analysis: Staff workshop with Houston Engineering (note that this is a
separate, parallel process from the plan update, but the information from the
analysis will be useful in planning the next ten years, so it is noted here)
• June 2020
• Hold the last of the issues workshops, engaging TAC members in small groups
• Begin holding joint board-council/town board workshops (workshop with Scandia
City Council occurred on June 22nd)
• June 25th regular board meeting: Board review and approve draft plan update
outline
• July 2020
• Bring proposed plan section drafting schedule to Board.
https://www.clflwd.org/documents/Agendaitem5c-WMPUpdate.pdf
• Begin discussing draft plan sections per schedule. Sections will be brought to board
meetings for discussion, posted to the District website, and sent to the District's
Technical Advisory Committee and Citizen Advisory Committee throughout the
summer.
• August 2020
• Continue holding joint board -council workshops (City of Wyoming)
• September 2020
• Continue holding joint board -council workshops (City of Forest Lake)
• Hold a full TAC meeting (via Zoom). This will be the first time the full TAC is
convened since the Initial Planning Meeting on June 20, 2019. The District has been
engaging TAC members in smaller groups through the issues workshops this spring
and via email with the draft plan sections throughout the summer.
• October 2020
• Final preliminary revisions, prepare full draft plan and seek Board approval to
submit for 60 -day review.
• November 2020
• Begin the first official review period, to last 60 days. Required review agencies will
be notified (BWSR, DNR, PCA, MDA, MDH, DOT, Met Council, counties, cities,
townships, SWCDs and adjacent WMOs/WDs), as well as the public (through the
District listserv, social media, newspapers, lake association meetings, etc.).
• January 2021
• 60 -day review ends. Respond to comments received and revise plan as necessary
(may take a few iterations over a couple of months, depending on how much input
is received).
• April 2021
• Early April: Goal to submit final draft plan to BWSR for 90 -day review.
• By this time, we will have a clear view of the 2022 CIP for budgeting purposes.
• July 2021
• BWSR completes its review and sends letter of approval or disapproval.
• July 15th regular board meeting: Board adopts updated plan. Afterward, staff
proceeds with distribution and printing.
• Plan to have WMP all wrapped up and finalized in advance of finalizing the 2022
District budget.
• September 2021
• September 28, 2021: Current Watershed Management Plan expires.