6. b Lilleskogen Park Eagle ProjectLilleskogen Park Eagle Project -Layout of Stepping stones on the path. -50 stones in total in a hopscotch pattern -stones will be spaced 2 feet away from the stones in front and behind -Rows with two stones will have the stones placed with 1.5 feet of room in between them. Composition of the Stones -Will be constructed using 5000 PSI concrete mix. -Will use polished river rocks for the numbers -Wire mesh will be inside of the stone for added strength 10 in. 2.8 in. Time frame December - February; Focusing on finalizing design and preparing materials. March; Construction of the stepping stones April; Installation of the stones as weather permits Installation information Holes will be dug with 10’’ diameter, approx. 2.5 inches deep. The troop will do installation themselves over the course of a day. The troop will provide all resources/ tools for the installation.