5. Engineer Comments - street project fundsCITY ENGINEER COMMENTS ON FUNDING THE 2021 STREET PROJECT CHANGE ORDER OR ALLOCATING FUNDS TO BROADBAND April 7, 2021 Ken, In regards to this memo in the packet, the total project budget was $895,000 per original approvals versus the $845,000 in the memo. ($845,000 was for the 220th and then City added $50,000 for the area on Layton Ave N – attached Authorization Council Memo from October 2020). Thus if we added $125,000 to fix Pomroy and taking out costs for permits, engineering, surveying, construction inspection, and materials testing; we conservatively estimate we would only have $21,000 - $31,000 remaining budget from the $895,000, thus there wouldn’t be the amount of $50,000 - $75,000 cost savings to be transferred to the internet expansion, but more closer to the $21K - $31K. By State statue we could have added up to $150,000 (25%) of bid award, but left the $21K - $31K cushion in the even we run into bad soils and need to do additional subgrade excavation. Thanks, Ryan J Goodman P.E. Bolton & Menk, Inc. 2035 County Road D East Maplewood, MN 55109-5314 Mobile: 612-597-7140 Bolton-Menk.com