9.c1 Engineering Updates 11-16-2021 City of Scandia Engineering Updates 11/16/2021 Engineering italics = old information · 2021 Street Improvement Project & Layton Ave N  City Council authorized Plans and Specifications for the 2021 Street Improvement Project at the October 20th City Council Meeting and Approved Plans & Specifications and Authorized Ad for Bid at the January 19th City Council Meeting.  Bid Opening was held on February 24, 2021 at 10:00am. March 16, 2021 City Council awarded the project to North Valley, Inc. and the Preconstruction Meeting has been scheduled for April 20, 2021, Contractor’s schedule will be discussed at that meeting and available for better updates at the City Council meeting.  Contractor paved bituminous driveways the week of May 24th. Contractor paved wear course on June 2nd and 3rd on Pomroy Avenue N/Peabody Trail N/220th Street N. These roads will be shouldered and gravel driveways will be resurfaced the week of June 7th. Layton Avenue wear course was paved on June 10th. Driveways were surfaced on June 16th. 220th Street and Pomroy Avenue N were striped on June 21st. Layton Ave ditch/restoration work was redone on July 15th. Watershed inspector to walkthrough site to potentially close out permit tomorrow Tuesday, August 10th.  As a separate agenda item, Contractor’s Request for Payment No. 4 and Final will be recommended for payment and project closeout. · Bliss Drainfield System  Both the 2020 permit application for this system and the “final report” for nitrogen mitigation have been completed and submitted to the MPCA. The memo which serves as a final report doesn’t present final solutions for the nitrogen issue, but instead outlines the issues that have been found and solved in this treatment system, as well as some additional testing that will now be recommended to get a handle on the nitrogen, BOD, and TSS entering and leaving the facility. The hope is to gain us a little more time from the MPCA before they mandate action. We’ll use this time to perform the aforementioned testing and evaluate options for removing nitrogen at Bliss.  City received on February 22, 2021 a Pre-Public Notice Review of Draft Permit - Bliss Collector WWTP (#MN0054119) that also included a statement of basis outlining any changes or new requirements to the draft permit. This 30 day pre-public notice review period starts on February 22, 2021 and ends on March 24, 2021. Once your pre-public notice review is complete the draft SDS permit will be placed on public notice for 60 days. · First thing that needs to be done is complete a Facility Evaluation Report within 180 days of issuance of the new permit they requested. Based on the report, MPCA will then ask the City to follow either Track 1 or Track 2. Track one is the new monitoring well. Track two is a facility upgrade. There are a few other changes to the permit, they include some additional monitoring required over this permit. Also, MPCA is requesting flow monitoring at WS 004, WS 005 and WS 006. These are to each of the infiltration trenches. We are in the pre-public draft notice stage where just the City received these draft documents and can comment. We can review and suggest changes or modifications prior to March 24th. · Current updates: Under track 1, the requirement to abandon GW 008 is included because using this well for monitoring is problematic, since we have no information on the well’s construction nor well boring records. Based on the limited information we do have, it is the opinion of MPCA hydrologist, Steven Stark, that this well is too deep to be used as a monitoring well and may be sampling a confined aquifer. All monitoring wells should be sampling the surficial aquifer and have well screens that bisect the watertable. · The justification for proposed timeline is sufficient and the new timeline will be incorporated into the draft permit. Shown below (last page of this report) is a revised compliance schedule. Flow monitoring requirements at WS 004, WS 005, and WS 006 will become effective upon installation of the flow monitoring equipment. The permit will continue to the 60-day Public Notice period.  The final permit has been issued. The assumption is that we’ll end up on Track 2, with required system improvements due to the nitrate issue. Only thing that needs to take place in the next 6 months (February 28, 2022) is for new flow meters to be installed at the system, something we’ll begin working on. At the one year mark (September 1, 2022), we’ll need to have a Facility Evaluation Report drafted to summarize the system’s ability or inability to meet the nitrate limit. · Sump Pump Inspection Program  2 homes/cabin remain to be inspected. · Bliss Addition Stormwater Planning  Recent engagement with the Carnelian Marine St. Croix Watershed District resulted in the two bullet points below: · Cost responsibility - Who would take on what costs and how? Ideally the District would like to participate with a Clean Water Fund Grant. · Timeline - The District is working to complete the Subwatershed analysis for Big Marine Lake. It will be complete by June 2021. Clean Water Fund Grants are awarded based on how the score. Without a completed Subwatershed analysis for the entire lake and application would score low. We planned to apply for a CWF grant in the fall of 2021 (after the completion of the analysis). If the City would like to dedicate funding and move up the timeline, they could request the CMSCWD Board of Managers consider funding a phase of the project without a CWF grant. I do know that next year’s budget is tight with the state required 10-year management plan update.  Temporary drainage improvements that included two options were presented at the August 5th City Council Workshop that were intended to relieve drainage concerns at the property of 19123 Layton Ave. Upon the discussion there seems to be separate opinions forming on both sides of the street of what temporary solutions are favored but why the ultimate correction is not just completed in conjunction with the storm sewer improvements identified in the neighborhood stormwater study.  On October 14, 2020 at the Watershed Board meeting, Board Managers approved $3,600 cost share for option 1.  Watershed anticipates in 2021 they will apply for 2022-2025 Clean Water Funds to implement stage 1 and 2, but could potentially also apply for all three stages. It should also be noted it will be difficult for the District to participate in just the directional pipe installation without the water quality BMPs being installed in that area. City may want to consider adding water quality practices to this stage to leverage more funds from District (with or without Clean Water Funds). · Stage 1 – directional drilled pipe to re-route drainage to wetland · Stage 2 – North Layton Ave bioinfiltration basin, concrete trench and enhanced ditch improvements, west bioinfilration basins, and 189th culvert crossings and enhanced ditches.  Watershed has completed the evaluation of potential projects on Big Marine. The Subwatershed Analysis is currently being prepared. Schedule still anticipates to be on track to apply for Clean Water Funds in July 2021.  Meeting scheduled with City Staff and Watershed District to discuss Clean Water Fund Grant Application on Thursday, July 22nd.  The final permit has been issued. The assumption is that we’ll end up on Track 2, with required system improvements due to the nitrate issue. Only thing that needs to take place in the next 6 months (February 28, 2022) is for new flow meters to be installed at the system, something we’ll begin working on. At the one year mark (September 1, 2022), we’ll need to have a Facility Evaluation Report drafted to summarize the system’s ability or inability to meet the nitrate limit. · CLFLWD Comprehensive Watershed Management Plan  60-Day Public Comment Period ended on April 30, 2021  Responses to comments were sent to review authorities on May 27, 2021. Visit: https://www.clflwdplanupdate.org/documents  The Board will hold a public hearing for the WMP on June 10, 2021. Visit: https://www.clflwd.org/6- 10-21_regular_board_meeting.php  The 90-Day Draft Plan was sent to the Board of Water and Soil Resources on June 15th  The BWSR Central Region Committee is scheduled to meet on Wednesday, August 4, 1- 3pm. This meeting will be held virtually (link/info forthcoming). It is during this meeting that CLFLWD staff will give a 5-10 minute presentation on the draft Plan and answer any questions the Committee may have.  The full BWSR Board will consider the Plan for approval at its meeting on August 25-26 (exact time TBD, but staff has been told that discussion/questions aren’t likely to occur at this time).  Board of Water and Soil Resources approved the Plan on August 26  CLFLWD Board adopted final Plan on September 23  Final printing/binding in progress. Distribution of final plan (either electronic version or printed version, depending on requirement) to all partners will occur by October 22 · CLFLWD & Scandia Staff Quarterly Meetings  Meeting held on October 19, 2020.  Meeting on February 9, 2021.  Meeting on May 11, 2021 covered the following topics: · Lake Management District Updates · Bone Lake projects status · Greenway Corridor Planning & Parks · Roadway projects · CMSCWD Managment Plan · Bone Lake H&H Modeling Update at 5/13 Board Meeting.  Meeting on September 13, 2021 covered the following topics: · Permitting Update · Roadway Projects · Tiller Mining and WD Boundaries · Bone Lake projects status (SE wetland restorations, NE wetland restoration, agricultural practices) · FY22 Clean Water Fund grant application – Moody Lake projects · Greenway Corridor Planning & Parks · CLFLWD Watershed Management Plan · CMSCWD Watershed Management Plan  Next quarterly staff meeting will occur sometime in Q4. Exact date TBD. · MnDOT/Washington County – Hwy 97 & Oakhill/CR 52  First initial contact/conference meeting with MnDOT to discuss issues and concerns with intersection safety on October 13, 2020. · This work has been completed; Signing – MnDOT will upgrade the size of all the fluorescent yellow-green signs and add fluorescent yellow green tape to the sign structure (the post). At the crossing itself MnDOT will be placing the enlarged signs back to back as to warn motorist on approach of the crossing on Hwy 97. These additions will enhance the visibility of the intersection. · Striping - The school Xing pavement markings were completed with the last pavement maintenance project, if City staff observes that these are worn out, please send in a request to MnDOT and they will submit it to our pavement makings crew.  County Road 52/Oakhill · City Council Workshop on June 2, 2021; Scandia City Council heard concerns residents who live along Oakhill Road, east of the business area, where they have observed speeding traffic and parking issues. One resident who lives at the site of the 30 mph zone remarked that the majority of drivers do not slow their speed at all and race in and out of town, causing safety concerns for the many pedestrians and bicyclists who share the road. · Washington County has scheduled a meeting with City Staff on June 21, 2021 to discuss the concerns brought forward to the City Council. · Coincidentally the County has been communicating with the City Engineer to discuss Oakhill, Highway 97, and Olinda Trail. We think this is a good time to have a conversation about overall traffic flow, pedestrian connections, speeding, bike routing, school issues, etc. in the “downtown” Scandia area and potentially start to develop a joint strategic plan for this entire area – including engaging MnDOT about improvements to highway 97. · CSAH 3 (Olinda Trail) Mill and Overlay Project · Construction Contact: Allan Brandt (651-430-4348) · If you would like to get these updates via email when they are available, sign up using the link on the web link: https://www.co.washington.mn.us/2899/County-Highway-3-Olinda-Trail · Contractor has finished the major work, currently working on site restoration and punch list items. · Floodplain Risk Assessment  Online Workshop held, January 5, 2021  The Brown’s Creek Watershed District (BCWD), Carnelian-Marine-St. Croix Watershed District (CMSCWD) and the Comfort Lake – Forest Lake Watershed District (CLFLWD) are jointly evaluating approaches to conducting a floodplain mapping/flood risk assessment with two goals in mind: · The short-term goal is to outline potential approaches the watershed districts could take to map and quantify future flood risk. · The long-term goal for these watershed districts is to build a common understanding of risk and prioritize projects and other resiliency actions.  Recommendations from consultants were to: 1. Conduct a GIS-based flood hazard assessment and workshop and 2. Model both historical and projected rainfall data to evaluate current design practices and inform future planning and management decisions.  CMSCWD has a completed Hydraulic and Hydrologic Model that was updated and calibrated in 2021. This model will be the foundation for any future climate resiliency modeling we conduct.  CMSCWD has identified climate resiliency/floodplain risk assessment work to be conducted in the 2023 in the CMSCWD Draft 10 Year Management Plan. The public comment period for the Management Plan ends October 15th and the public hearing for the final plan is scheduled for November 18th. · 191st Street N and Kirk Ave/220th Street N Pavement Maintenance Project  Contractor’s Request for Payment No. 2 and Final was approved at the October 19th City Council Meeting. · Uptown Drainfield System Capacity Review  Recent inspection of interior of pumped-down EQ tank by Smilie’s didn’t detect any apparent sources of I/I – we still don’t know where the additional flow that seems to be reaching the treatment system is coming from.  Recently received some info which should help us predict flows from the downtown café once it reopens.  After a final review we’re looking at allowing the proposed Heritage Center to connect to the existing system without modification. However, we’d like one more specialist to take a look at the system, specifically the drainfields, and verify that there isn’t evidence of an immediate capacity problem. We’re currently working with this specialist to schedule a time for him to do a site visit in the next 1-2 weeks. · Regional Update – Highway 243 Osceola Bridge  MnDOT are in process of designing the reconstruction of the Hwy 243/Osceola Bridge over the St. Croix National and Scenic Riverway, in partnership with the Wisconsin Department of Transportation (WisDOT). The Osceola Bridge was built in 1953.  The purpose of this project is to maintain a reliable highway connection over the St. Croix River for Hwy 243 between Washington/Chisago counties in Minnesota and the Village of Osceola and Polk County in Wisconsin. The project team will work with federal, state and local interests to minimizing project impacts to the St Croix River and other natural resources in the area.  Project website: http://www.dot.state.mn.us/metro/projects/hwy243osceola/index.html  Schedule: · Environmental documentation and preliminary design: 2021 through 2023 · Final design: 2023 through 2025 · Anticipated construction: 2025 through 2026 · CMSCWD 2022-2031 Watershed Management Plan and Rule Revision  CMSCWD Rule Revisions: · The rule revisions were very minor. No substantial change to the intent per the previous set of rules. Simply minor comments to address concerns surrounding “direct conveyance to a groundwater repentant natural resources or public water”. · The Watershed Management Plan states that a more significant revisions could be in the next 3 to 5 years.  CMSCWD Watershed Plan: · Bliss Addition Improvements listed as future projects for Big Marine. · The water quality improvement, flood protection, wetland mitigation, and public out reach goals all seem very achievable and will be accomplished proactively by the district with partnerships. · Page 70: “District Rules may be significantly revised in 2024/2025 in conjunction with a voluntary grant program for communities to update stormwater and shoreland ordinances and other controls by local government units. The Minnesota Minimal Impact Design Standards (MIDS), or similar, may be incorporated at that time for consistency among neighboring communities.” o This will be a worthwhile effort for communities in CMSCWD, especially if grant money is available, such that local ordinances match the watersheds approach. This will dramatically simplify permitting. o Scandia should continue to partner with the district on their regulatory program in preparation for this potential change. o Scandia should be especially aware as they have two watersheds. How will this impact CLFLWD? Would they be willing to implement a new ordinance if it deviates from CLFLWD rules? Would CLFLWD be willing to do the same? · Gateway Trail Planning  Meeting with Washington County has been scheduled for Monday, November 29, 2021 to discuss partnership on Gateway Trail Planning opportunities within Scandia. · Martin Marietta Mine (old name Tiller Mine)  Annual site inspection has been scheduled for Friday, November 12, 2021. · Washington County – Draft Capital Improvement Plan (CIP) 2022 – 2026  Washington As part of the annual budget process, Washington County prepares a five-year Capital Improvement Plan (CIP). The 2022-2026 CIP includes the county's tentative plans for roads, bridges, parks, land, trails, transit, and public facilities. The first year of this plan is included in the county's proposed 2022 budget. The “out-years” of 2023-2026 reflect projected needs and estimated costs, which may change based on future priorities and funding opportunities.  Draft CIP link: https://www.co.washington.mn.us/DocumentCenter/View/48917/DRAFT- 2022-2026-Capital-Improvement-Plan  Comments must be received in writing no later than November 19, 2021, to be considered when developing the final CIP. A public hearing will be held on November 30, 2021, and formal adoption is scheduled for December 14, 2021.  DRAFT COMMENTS ATTACHED TO REPORT AT END 14727 209 th St. N. PO Box 128, Scandia, Minnesota 55073 Phone (651) 433-2274 Fax (651) 433-5112 http://www.ci.scandia.mn.us November 16, 2021 Larry Phillips Washington County Office of Administration 14949 62nd Street North Stillwater, MN 55082 Re: Washington County 2022-2026 Draft Capital Improvement Plan Comments Dear Washington County, The City of Scandia would like to provide comment on the Washington County 2022-2026 Capital Improvement Plan (CIP), by expressing our support for the following planned projects: · Project RB-2680 Scandia City Center Study. The scope of this study is to investigate the existing and future pedestrian, bicycle, and vehicular needs in the downtown Scandia area in order to develop a transportation planning vision for county routes through the City of Scandia. · Project RB-2682 County Road 50. The project scope includes the following improvements on County Road (CR) 50 from Trunk Highway (TH) 61 to CSAH 15 (Manning Trail North): new pavement with widened shoulders, turn lanes at key locations if appropriate, evaluation of pedestrian and cycling accommodations, signs and striping, roadway drainage and surface water management, roadway geometrics evaluations. We would also like to inquiry what happened to the other projects that were listed in previous Plans: · Project RB-2204 to include pavement preservation & rehab on CSAH 3 from Old Marine Trail to County line. · Project RB-2673 CSAH 15 Rumble Strips – planned 2025 construction projects, request the County review the installation of mumble strips versus traditional rumble strips on CSAH 15 (Manning Ave) from CSAH 12 to 240th Street which is the county line. We would also like to provide our support on the plan incorporating the following projects: · Intersection improvements at CSAH 15 & Hwy 97 · Intersection evaluation and safety improvements at County Road 52 and Hwy 97 · Implement within the CIP by identifying studies, funding, and/or provide resources to assist the DNR in pursuing regional trail development and better connectivity throughout northern Washington County. 14727 209 th St. N. PO Box 128, Scandia, Minnesota 55073 Phone (651) 433-2274 Fax (651) 433-5112 http://www.ci.scandia.mn.us The intersection of County Road 52 & Hwy 97 brings additional concerns with its skewed alignment that limits driver and pedestrian sight distance when trying to cross the intersection. The City requests this intersection be added to the CIP for the County to complete an intersection evaluation and to implement low cost-high benefit safety improvements at the intersection that may include improved intersection lighting, enhanced signing, and installation of intersection conflict warning system. The City has initiated conversations with MnDOT but looking for a County present to be involved in this process. The intersection of CSAH 15 & Hwy 97 has been the source of concern for many years and the City has submitted comments on this intersection on past draft CIP’s. This intersection experiences backups at AM & PM peak hours and is an intersection that has had many close calls that could have resulted in serious T-bone crashes. The City requests this intersection be added to the CIP that would include future intersection improvements. The City also would like to request the County complete an intersection study in 2021 in coordination with MnDOT at this intersection so future improvements or project constraints can be identified. Thank you for allowing our comments to be submitted on the Washington County 2022-2026 Draft CIP. Sincerely, Ryan J. Goodman, P.E. City Engineer