Loading...
8.d Engineering Updates City of Scandia Engineering Updates 5/17/2016 Engineering • 2016 Street Improvements 1. Contractor started work on May 9 th . Work completed to date includes placement of erosion control and traffic control, reclaiming existing road base, and culvert replacements. 2. Work is anticipated to be completed by the end of the June 2016. • 2016 Seal Coat and Crack Filling Project 1. Project is scheduled to start July 25 th or later unless the street patching work is completed sooner. If the street patching is completed earlier than we will work with the Contractor on potentially scheduling the work sooner. • Log House Landing Boat Launch 1. Been assisting City Staff by providing technical information for the plan development of the concrete boat launch. • Washington County – Intersection of Hwy 97/CR 91 (Lofton Ave) 1. Work completed to date includes: clearing & grubbing, shifted traffic to the EB lane/shoulder, and excavated and graded the widening on the north side of the project. 2. Next milestones will include: pave bottom lifts north of the barriers (5/16), Remove temporary barriers (5/24), Pave final lift across the entire project (5/25), Substantial Completion (5/26), and Final Completion (6/4). • Sand Lake Iron Enhanced Sand Filter Project 1. Project work has been completed other than some minor punch list items that have been identified by the Watershed which are anticipated to be completed by the end of the month. Overall project went well and the watershed will monitor the site for results to be reported.