8.d1 May Engineering Updates City of Scandia Engineering Updates 6/21/2016 Engineering • 2016 Street Improvements 1. All culvert work was completed the week of June 13 th . Placement and preparation of Class 5 material continued the week of June 13 th and is anticipated to be completed the early part of June 20 th . Bituminous paving is planned to start the week of June 27 th if not earlier. • 2016 Seal Coat and Crack Filling Project 1. Project is scheduled to start July 25 th or later unless the street patching work is completed sooner. If the street patching is completed earlier than we will work with the Contractor on potentially scheduling the work sooner. • Bliss Drainfield System 1. Engineering Staff will be attending the June 23 rd Wastewater Committee on June 23 rd to specifically discuss testing results, and existing & future permit requirements. • Washington County – Intersection of Hwy 97/CR 91 (Lofton Ave) - Completed • Sand Lake Iron Enhanced Sand Filter Project - Completed